Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/02/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* 1) BLDG INSPECTOR TO OBTAIN LANDSCAPING BACKFLOW CERTIFICATION |
|
| 01/31/2006 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* ONLY ITEM #5 REMAINS FOR FINAL |
|
| 01/24/2006 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. TERMINATE ALL EXTERIOR CLEANOUTS CORRECTLY 2. PROVIDE VACUUM BREAKERS AT ALL HOSE BIBS 3. SEAL ALL PIPE PENETRATIONS INTO BUILDING 4. TERMINATE WATER HEATER TEMPERATURE & PRESSURE RELIEF DRAIN WITH 90 DEG. DOWN 5. SHOW COPY OF PERMIT FOR NEW BACKFLOW DEVICE FROM TUCSON WATER FOR MAIN AND PROVIDE COMPLETION OF WATER CONNECTION FOR LANDSCAPING SUPPLY WITH CERTIFICATION OF IT'S BACKFLOW DEVICE. 6. PROVIDE DIELECTRIC CONNECTION FOR COLD SUPPLY TO WATER HEATER. 7. CALL IN 03040 & 03075 FOR INSPECTION WITH 03090 FINAL. |