Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T05CM00770
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/17/2005 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) LAST OF THE TRENCH DRAINS INSTALLED OK 2) OK TO COVER ALL UNDERGROUND |
|
08/16/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
08/15/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. TRENCH DRAINS AS DISCUSSED WITH CONCRETE CONTRACTOR OK TO COVER. |
|
08/09/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) OK TO POUR NEXT SECTION 2) ? DRAINS OK 3) PIPE WRAP OK |
|
07/21/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) PRE-SLAB PIPE WRAPS OK FOR NORTH EAST CORNER AREA CENTER LINE F TO EAST |
|
07/14/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) OK TO POUR TWO AREAS REVIEWED WITH PLUMBER |
|
06/28/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) NOT INSTALLED PER PLAN REDLINES ON SITE. OK TO COVER SUBJECT TO REVISED APPROVED PLAN. 2) CALL 3005 FOR PRE POUR INSPECTION. | |
06/27/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
06/20/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* NOT READY REVIEW 103.5.4.2 RESPONSIBILITY TO BE READY. | |
06/17/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | 1) OK TO COVER TRUNK LINE-SUBJECT TO REVISED APPROVED PLAN. 2) CALL FOR TROUGH DRAINS, FLOOR DRAINS, FLOOR SINKS PRE-POUR. | |
06/15/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* 1. IT'S HOT!!. 2) NOT READY | |
06/13/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
06/10/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) COMBINATION WASTE, VENT AND CONVENTIONAL SYSTEMS MAY NOT BE MIXED. PLAN APPROVED IN ERROR 2) SEE APPENDIX B ILLUSTRATED TRAINING MANUAL 1994 3) NORTH 4" ABS MAIN FROM EAST SIDE TO WEST SIDE END OF RUN CLEANOUT OK TO COVER |