Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/26/2007 | ELECTRIC - FINAL | Approved | IVRS - Inspection :* REMOVE PAINT UNDER WATER BOND CLAMP AND RETIGHTEN |
|
| 11/15/2007 | ELECTRIC - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1. INSTALL GROUND RODS AND BOND WATER AND GAS PIPES SEE PLAN 2. LIGHTING CONTACTOR TO HAVE PROPER J-BOX ENCLOSURE AND COVER 3. SEAL ALL UNUSED OPENINGS IN EQUIPMENT 4. PANEL DIRECTORY TO BE CORRECT & LEGIBLE 5. GROUNDS & NEUTRALS TO BE SEPARATED IN SUB-PANEL, SELF TAP SCREW NOT ALLOWED FOR GROUND CONNECTION 6. USE PROPER (GE) BREAKERS IN GE PANEL 7. IDENTIFY & GROUND PROEDGE DISCONNECT 8. SECURE ALL BOXES TO STRUCTURE, INSTALL ALL COVER SCREWS 9. IDENTIFY PHASES FOR CONDUCTOR |
|
| 11/05/2007 | ELECTRIC - FINAL | Not ready for Inspection | IVRS - Inspection :* PLANS NEED TO BE REVISED TO SHOW ACTUAL SCOPE OF WORK |
|
| 09/07/2006 | ELECTRIC - FINAL | Denied | IVRS - Inspection : The wiring is not complete or does not comply with code.| 245* REVISE PLAN TO SHOW ACTUAL WORK DONE AND AFTER INSTALLATION IS COMPLETE AND PER PLAN CALL FOR FINAL. |
|
| 09/06/2006 | ELECTRIC - FINAL | Denied | IVRS - Inspection : ELECTRICAL COVERED AT FINAL INSPECTION, HAVE THE ELECTRICAL CONTRACTOR WHO DID THE WORK ON SITE TO OPEN EQUIPMENT AND GO OVER INSTALLATION WITH ME |