Permit: T05BU02883

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
05/15/2019 STORMWATER FOLLOW-UP INSP Approved THIS PERMIT HAS BEEN FINALED AT THIS TIME SINCE ALL WORK HAS BEEN COMPLETED IN THE PAST.
11/25/2008 STORMWATER FOLLOW-UP INSP Correction Required STORMWATER CONTROLS ARE DETERIORATING AND NEED MAINTENANCE.
THE STREETS ARE LACKING THE FINAL 2" ASPHALT OVERLAY

NO CONSTRUCTION AT THIS TIME.
THIS IS A 19 LOT SUBDIVISION. THERE ARE (7) UNBUILT LOTS, WITH (2) PARTIALLY CONSTRUCTED HOMES. ONE OF THE PARTIALLY CONSTRUCTED HOMES AT 7333 E VUELTA RANCH MESQUITE TAX PARCEL #114-476120 HAD A NOTICE OF TRUSTEE'S SALE DATED 7/1/08 WITH A SALE DATE OF 9/30/08

AMERICABUILT CONSTRUCTION INC.,
5255 E. WILLIAM CIRCLE #6000

BANK OF THE WEST
7225 N. ORACLE RD #202
TUCSON, BBC 21041
08/13/2007 STORMWATER FOLLOW-UP INSP Partial Approval RICK BERGMAN - 404-5821 IS HANDLING SITE SWPPP
NO STORMWATER CONCERNS.0
08/08/2007 STORMWATER FOLLOW-UP INSP Correction Required 1. LOT SWPPP CONTROLS NEED MAINTAINENCE.
2. STREETS NEED TO BE SWEPT OF SAND AND SOIL.
03/08/2007 STORMWATER FOLLOW-UP INSP Partial Approval BMP'S ARE IN PLACE
02/28/2007 STORMWATER FOLLOW-UP INSP Correction Required 1. SWEEP STREETS OF ALL SEDIMENT AND SOIL.
2. PROVIDE SWPPP CONTROLS FOR ALL LOTS WITH DISTURBED SOIL OR THAT ARE UNDER CONSTRUCTION
3. PROVIDE UPDATED NOI AND POST AT THE ENTRANCE
JERE 730-2237
01/31/2007 STORMWATER FOLLOW-UP INSP Correction Required MORE STRAW WATTLE IS NEEDED ON NORTH PERIMETER OF LOT 108
01/30/2007 STORMWATER FOLLOW-UP INSP Correction Required 1. PROVIDE SEDIMENT AND EROSION CONTROLS ON PERIMETER OF LOTS 117 & 108 AND AT R/D BASIN INLET.
12/05/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO STORMWATER CONCERNS.
11/28/2006 STORMWATER FOLLOW-UP INSP Correction Required 1. SWEEP STREETS TOMORROW WHEN SWEEPER IS REPAIRED
2. REMOVE SAND DUMPED ON PAVEMENT AT SOUTH PERIMETER.
3. REPLACE SWPPP CONROLS ON NORTH PERIMETER WHERE NEEDED AS SIDEWALKS ARE INSTALLED.
11/08/2006 STORMWATER FOLLOW-UP INSP Correction Required 1. UPDATE THE SWPPP DOCUMENTS.
2. PROVIDE A CURRENT N. O.I. AND POST ON-SITE.
3. PROVIDE CONTRACTOR/SUBCONTRACTOR CERTFICATIONS IN SWPPP BOOK.
4. CONTROL DUST ON SITE ANDADJACENT STREETS AT ALL TIMES.
11/07/2006 STORMWATER FOLLOW-UP INSP Correction Required 1. SWEEP PRIVATE STREETS ADJACENT TO SITE DAILY.
2.PROVIDE SWPPP CONTROLS AT SITE PERIMETER AT THE END OF EACH DAY.
3. REPLACE BROKEN GRAVEL BAGS AT NE END OF PROJECT ON STREET.
4. CLEAN UP CONCRETE WASHOUT AND STUCCO WASHOUT AT ALL AREAS OUTSIDE OF DESIGNATED CONCRETE WASHOUT AREA.
5. APPLY COLD PATCH ON PAVEMENT CUTS ON SOUTH PERIMETER OF SITE TO PROVIDE AT MINIMUM (1) LANE OF THRU TRAFFIC.
6. PROVIDE APPROVED DETAIL FOR PAVING ON VACTOR RANCH TRAIL AND VUELTA RANCHO MESQUITE.
11/02/2006 STORMWATER FOLLOW-UP INSP Correction Required 1. PROVIDE COMPLETE SITE PERIMETER STORMWATER CONTROLS.
2. SWEEP ADJACENT STREETS EVERYDAY AS PROMISED.
3. PROVIDE STABILIZED CONSTRUCTION ENTRANCES AT (2) LOCATIONS FOR NORTH AND SOUTH ENDS OF SITE.
4. PROVIDE ALL STORMWATER REPORTS ON SITE.
10/03/2006 STORMWATER FOLLOW-UP INSP Partial Approval SITE VISIT TO CHECK STREETS AND DUST CONDITIONS.
10/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval SITE VISIT TO CHECK STREETS AND DUST CONDITIONS.
09/28/2006 STORMWATER FOLLOW-UP INSP Correction Required SUFFICIENT COMPLIANCE HAS BEEN OBTAINED TO PREVENT CITATION AND STOP WORK ORDER.
1. CLEAN UP HOME BUILDING DEBRIS DAILY.
2. SWEEP STREETS DAILY.
3. WATER DOWN SITE TO CONTROL DUST AT LEAST DAILY.
4. PROVIDE UPDATED N.O.I.
09/27/2006 STORMWATER FOLLOW-UP INSP Correction Required 24 HOUR CORRECTION NOTICE ISSUED AT 1300 HOURS, NON-COMPLIANCE WILL RESULT IN CITATIONS AND STOP WORK ORDER.
1. REMOVE DIRT STOCKPILES FROM STREETS AND SIDEWALKS.
2. SWEEP STREETS AND SIDEWALKS.
3. REMOVE TRASH ACCUMALATION, BROKEN PAVEMENT AND CONCRETE WASHOUT.
4. REPAIR OR REPLACE SWPP CONTROLS AT PERIMETERES OF SITE.
5. PROVIDE A MATERIALS STORAGE AREA ON SITE PER BMP 101.
6. PROVIDE UPDATED COPY OF THE N.O.I..
09/08/2006 STORMWATER FOLLOW-UP INSP Correction Required PROVIDE THE UPDATED COPY OF THE SWPPP ON SITE AT ALL TIMES AND COPIES OF INSPECTION REPORTS ADN CONTRACTOR/SUBCONTRACTOR CERTIFICATIONS.
2. SEDIMENT, EROSION AND DUST WILL BE CONTROLLED AT ALL TIMES, INCLUDING ALL EXCAVATION FOR UTILITIES PROJECTING INTO THE EXISTING PAVED STREETS.
3. ALL TEMPORARY SWPPP CONTROLS WILL BE IDENTIFIED IN THE SWPPP.
09/05/2006 STORMWATER FOLLOW-UP INSP Correction Required CORRECTION ORDER ISSUED FOR COMPLIANCE BY TOMORROW OR A NOTICE OF VIOLATION, CITATIONS AND STOP WORK ORDER WILL BE ISSUED.
1. SWEEP THE STREETS ON THE PERIMETER OF ALL MUD AND SEDIMENT.
2. COMPLETE ALL MAINTENANCE OF SWPP CONTROLS AT THE PERIMETER OF THE SITE.
3. UPDATE THE SWPPP TO SHOW ALL CURRENT SWPP CONTROLS AND STABILIZED CONSTRUCTION ENTRANCES.
4. UPDATE THE SWPPP WITH COPIES OF THE CONTRACTOR/SUBCONTRACTOR CERTIFICATIONS (SEE SECTION 13 OF THE SWPPP).
5. REMOVE SEDIMENT FROM THE DRAINAGE CHANNEL DOWNSTREAM OF THIS PROJECT.
6. REMOVE DIRT STOCKPILES AWAY FROM THE SOUTH PERIMETER.
7. MOVE TRASH CONTAINERS OFF THE SILT FENCE AND AWAY FROM THE PERIMETER.

SIGNIFICANT PROGRESS TOWARDS COMPLIANCE MUST BE COMPLETED TOMORROW TO PREVENT FURTHER ENFORCEMENT ACTION.

RICK BERGMAN (609-9388) AMERICAN BUILT HOMES SUPERINTENDENT SIGNED THE CORRECTION NOTICE.

I ALSO MET WITH BILL KOCH (909-5979) AND JIM SOMERSET OF AMERICAN BUILT HOMES.
09/01/2006 STORMWATER FOLLOW-UP INSP Correction Required CORRECTION ORDER GIVEN FOR COMPLIANCE BY TUESDAY 9-5-06 OR NOV AND STOP WORK ORDER WILL BE ISSUED.
1. PROVIDE STABILIZED CONSTRUCTION ENTRANCES AND SWPPP CONTROLS AT THE NORTH PERIMETER.
2. SWEEP STREET CLEAR OF ALL SEDIMENT.
08/22/2006 STORMWATER FOLLOW-UP INSP Correction Required I SPOKE TO BILL KOCH, HE WILL DIRECT UNDERGROUND CREW REGARDING SWPPP.
SOME OF THE SWPPP CONTROLS ARE IN PLACE, BUT DUE TO THE UNDERGROUND WORK AT THIS TIME, SWPPP WILL HAVE TO BE MONITORED FREQUENTLY BY BILL KOCH.
NORTH PERIMETER CONTROLS NEED TO BE MAINTAINED.
08/14/2006 STORMWATER FOLLOW-UP INSP Correction Required COMPLETE ITEMS I,2, AND 5 OF PREVIOUS INSPECTION.
1. PROVIDE STABILIZED CONSTRUCTION ENTRANCE.
2. RE-INSTALL AZPDES AUTHORIZATION POSTING.
5. REMOVE SEDIMENT FROM DRAINAGE CHANNEL DOWN GRADIENT FROM THIS SITE.
08/14/2006 STORMWATER FOLLOW-UP INSP Correction Required SEE NOTES 1,2 AND 5 OF PREVIOUS INSPECTION.
08/07/2006 STORMWATER FOLLOW-UP INSP Correction Required 1. PROVIDE STABILIZED CONSTRUCTION ENTRANCE.
2. RE-INSTALL AZPDES AUTHORIZATION POSTING.
3. SWEEP DIRT OFF THE STREET.
4. PROVIDE SWPPP CONTROLS AT THE DRAINAGE CHANNEL DOWN GRADIENT FROM THE SEWER LINE CONSTRUCTION PROJECT.
5. REMOVE SEDIMENT FROM DRAINAGE CHANNEL DOWN GRADIENT FROM THIS SITE.
07/10/2006 STORMWATER FOLLOW-UP INSP Partial Approval CORRECTION COMPLETE, SEWER TIE IN AND BY PASS WILL BE CONSTRUCTED THIS WEEK.
06/30/2006 STORMWATER FOLLOW-UP INSP Correction Required NO CHANGES I LEFT A MESSAGE FOR BILL KOCH 909-5979, AND CALLED RICK BERGMAN/AMERICABUILT HOMES 609-9388, WHO SAID HE WOULD HAVE ROCK DOWN ON ENTRANCE ON 7/3/06.
06/23/2006 STORMWATER FOLLOW-UP INSP Correction Required CONSTRUCTION ENTRANCE NEEDS MORE ROCK. I LEFT A VOICE MAIL FOR BILL KOCK 298-0587
05/25/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO STORMWATER CONCERNS