Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T05BU02853
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/09/2006 | GRADING - INTERMEDIATE | Approved | SEE FINAL GRADING FOR ALL COMMENTS | |
| 11/07/2006 | GRADING - INTERMEDIATE | Correction Required | MET WITH PAUL MACHADO CHANGES TO DRAINAGE PIPE ON WEST SIDE OF SITE MUST BE REFLECTED ON A REVISED GRADING PLAN INCLUDING: ELEVATIONS, PIPE SLOPE AND MAINTENANCE AGREEMENT WITH DAR-HIL OUTSTANDING GRADING ISSUES: BASIN CERTIFICATION LETTER OFF SITE CLEAN UP AT WALL AND LANDSCAPING OFF SITE CLEAN UP AT DRAINAGE INLET WITH LANDSCAPING MISSING STRIPING AT ASPHALT PATCH |
|
| 06/19/2006 | GRADING - INTERMEDIATE | Correction Required | -SITE HAS NOT BEEN STABILIZED AT NORTH CATCH BASIN -CURB HAS NOT BEEN REPLACED -DRAINAGE PIPE IS NOT AT PLAN ELEVATION-CHANGES NEED TO BE SUBMITTED TO AND REVIEWED BY C.O.T. -VACTOR TRUCK MUST BE USED ON NEW DRAINAGEWAY BEFORE SEDIMENTS ARE PUSHED INTO C.O.T. STORMDRAIN SYSTEM |
|
| 05/23/2006 | GRADING - INTERMEDIATE | Partial Approval | SPOKE TO WYATT WITH DAR HIL SPLASH PAD AT NORTH AND SOUTH END OF DRAINAGE WAY ARE TO BE POURED THURSDAY |
|
| 04/24/2006 | GRADING - INTERMEDIATE | Partial Approval | I WAS ADVISED THAT DRAINAGE PIPE HAS .5' OF FALL PLANS CALL FOR 3' OF FALL PER SITE SUPER BRUCE CALL HAS BEEN SPEAKING WITH SOME ONE AT THE COT AND THIS HAS BEEN ACCEPTED? |
|
| 04/11/2006 | GRADING - INTERMEDIATE | Partial Approval | WATCHED THE CATCH BASIN BEING SET ON SW CORNER OF PROJECT MASTIC WAS INSTALLED AND HAYDEN WILL GROUT 4/12 |
|
| 02/22/2006 | GRADING - INTERMEDIATE | Partial Approval | TALKED WITH DON OKLAND CONST WALL GOING UP WILL REPLACE SEDIMENT CONTROLS AT PERIMETER |
|
| 02/21/2006 | GRADING - INTERMEDIATE | Partial Approval | CMP BEING INSTALLED NW CORNER FOR DRAINAGE TIE IN | |
| 01/05/2006 | GRADING - INTERMEDIATE | Partial Approval | MET WITH DONALD (OKLAND CONST) MOVING JOB TRAILER ON SITE AND GETTING READY TO START THE FORMS FOR FOUNDATION | |
| 12/22/2005 | GRADING - INTERMEDIATE | Partial Approval | SPOKE TO RICK SHERMAN (DAR-HIL) ON SITE. LASER LEVEL WAS SET UP AND SURVEYORS STATE (SHOT) FFE IS 5.85 ABOVE ROAD PRISM. THIS IS CONSISTENT WITH APPROVED PLANS ON SITE/ON FILE |