Permit: T05BU02539

Parcel: 13711423B


Addresses:

1650 W IRVINGTON RD

Inspection Status: Continued

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
05/12/2011 STORMWATER FOLLOW-UP INSP Continued THE JR TUTTLE CO WORKING ON ROOF NO CHANGE TO SWPPP FROM PAST INSPECTION.
03/16/2011 STORMWATER FOLLOW-UP INSP Continued NO ACTIVITY AT IS TIME.
09/04/2008 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to clean and stabilize areas next to wash.
08/25/2008 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address SWPPP issues on site. Spoke to Rudy in regards to.
06/03/2008 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address construction traffic exiting site from northwest corner. Contractor will need to stabilize area disturbed by construction.
04/07/2008 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity on site at this time.
10/17/2007 STORMWATER FOLLOW-UP INSP Partial Approval No activity on site at this time. Contractor continues to work on wash cuts.
08/08/2007 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to Rudy on 8/2/07, I explained to Rudy it was ok to set both catch boxes and run piping. But wash cut should be completed one at a time.
07/02/2007 STORMWATER FOLLOW-UP INSP Partial Approval No activity.
06/12/2007 STORMWATER FOLLOW-UP INSP Partial Approval No activity, contractor installed chain gate front of project.
05/16/2007 STORMWATER FOLLOW-UP INSP Partial Approval Controls in place. Contractor continues to work on perimeter wall.
05/02/2007 STORMWATER FOLLOW-UP INSP Partial Approval No activity at this time.
04/02/2007 STORMWATER FOLLOW-UP INSP Partial Approval No activity at this time. Contractor continues to work on perimeter wall.
02/26/2007 STORMWATER FOLLOW-UP INSP Partial Approval Controls in place. No concerns at this time.
02/07/2007 STORMWATER FOLLOW-UP INSP Partial Approval No activity, controls in place.
01/09/2007 STORMWATER FOLLOW-UP INSP Partial Approval Controls in place.
12/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval Wattle in place, no concerns at this time.
12/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time.
10/24/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time. Contractor installed perimeter wall from entrance to west corner. Contractor started digging footer for building.
10/05/2006 STORMWATER FOLLOW-UP INSP Partial Approval Repair silt fence or extend wattle on northwest side of project.
09/21/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor installed wattle along northside. Contractor starting to install block wall of southside.
08/31/2006 STORMWATER FOLLOW-UP INSP Correction Required Met Mike site super on site (Wed. 8/30) went over correction that need to be made to SWPPP controls. I Explained to Mike if temp controls are not installed by the next inspection I will issue a Notice of Violation for allowing a discharge into the wash.
40' of perimeter wall fell down.
Basin holding water for more then 24 hours. (5 days)
08/16/2006 STORMWATER FOLLOW-UP INSP Correction Required Met Mike on site went over SWPPP issues. I explained to Mike temp controls have to install in erosion area next to Santa Cruz.
08/15/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor has not addressed items from last inspection 8/2/06. Spoke to Rudy at approx. 1500 hours and went over items that need to be addressed. I told Rudy if the items are not addressed I would issue a NOV. Rudy asked me to call Michelle Guy in regards to repairs in wash area.
08/02/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to repair/replace stormwater controls. Repair erosion on wash bank. Contacted Rudy site super via cell 591-0485.
07/19/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to repair/replace stormwater controls northeast corner. Contacted Rudy via cell phone in regards to issues.
06/20/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to repair hole in fence northeast corner.
06/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time. Contractor cleaned wash out from last inspection.
05/22/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to clean up concrete and mason wash out around site. Contractor needs to provide proper wash out area for subs. Spoke to Rudy Ruiz in regards to issue.
05/08/2006 STORMWATER FOLLOW-UP INSP Partial Approval Need to keep eye on northeast corner of project.
04/24/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor starting perimeter wall on west side.
04/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor completed entrance off of Irvington. No stormwater concerns at this time.
03/20/2006 STORMWATER FOLLOW-UP INSP Partial Approval OK to remove some silt fencing on eastside. 90 feet on northeast corner to remain running south.
03/09/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor installed wattle on south side of project.
02/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval Met with Gilbert on site and discussed additional waddle to be installed from the construction entrance to the southwest corner. Gilbert said he would have it installed soon.
02/23/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor installing construction entrance off Irvington Rd. Set up meeting with Gilbert for Tuesday 2/28/06 at 1100 hours, in regards to additional stormwater controls on southwest side.
02/06/2006 STORMWATER FOLLOW-UP INSP Partial Approval Talked to Gilbert in regards to contractor using property next to project for access. I explaioned to Gilbert he will need to get a construction easement for the property. Gilbert told me he thought they had an easement and would fax me the paper work. I received on 2/7/06. Also conctractor needs to remove dirt ramp from roadway.
01/24/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.
01/10/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity at this time.
12/19/2005 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity at this time.
12/05/2005 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity at site.