Permit: T05BU02505

Parcel: 13614011E


Addresses:

8200 E STELLA RD

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
03/11/2011 STORMWATER FOLLOW-UP INSP Approved
07/10/2006 STORMWATER FOLLOW-UP INSP Correction Required WATTLES HAVE BEEN MOVED
ADDITIONAL CONTROLS MAY BE NEEDED ALONG EAST SIDE OF STOCKPILE
06/19/2006 STORMWATER FOLLOW-UP INSP Correction Required SILT FENCES ARE DOWN
05/22/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CONCERNS
05/15/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CHANGE IN SITE
04/28/2006 STORMWATER FOLLOW-UP INSP Correction Required NO CHANGE IN SITE
04/24/2006 STORMWATER FOLLOW-UP INSP Correction Required NO CHANGE IN SITE
04/11/2006 STORMWATER FOLLOW-UP INSP Correction Required SILT FENCE HAS BEEN KNOCKED DOWN AGAIN (VANDALISM) ALONG EAST SIDE OF STOCKPILE AND ALONG PARTS OF NORTH SIDE
SWPPP POSTING HAS BEEN KNOCKED OVER (VANDALISM)
03/29/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CHANGE IN SITE
03/22/2006 STORMWATER FOLLOW-UP INSP Approved VISTED SITE WITH BEV
WE WALKED THE SITE AND SAW NO EXISTING ROADWAY TRANVERSING THE WASH
THERE HAS BEEN QUITE A BIT OF DUMPING IN THE WASH AREA AND IN FUTURE PROJECT AREA
03/21/2006 STORMWATER FOLLOW-UP INSP Partial Approval SILT FENCE HAS BEEN RESET
03/16/2006 STORMWATER FOLLOW-UP INSP Correction Required SILT FENCE ALONG NORTH AND WEST SIDES OF PROJECT NEEDS TO BE RESET
03/09/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CHANGE IN SITE
03/03/2006 STORMWATER FOLLOW-UP INSP Correction Required SILT FENCE POSTS NOT REPLACED AS PROMISED BY ED CRADDOCK DURING PHONE CALL 3/1
02/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO CHANGES IN SITE
02/22/2006 STORMWATER FOLLOW-UP INSP Partial Approval DROVE BY SITE
NO CHANGES
02/21/2006 STORMWATER FOLLOW-UP INSP Partial Approval 3:1 SLOPE PARTIALLY ADDRESSED
SWPPP CONTROLS IN PLACE AND APPEAR TO BE WORKING
GRADING PLAN APPROVED/RCVD
02/13/2006 STORMWATER FOLLOW-UP INSP Partial Approval NO ADDITIONAL WORK DONE ON SITE YET
02/08/2006 STORMWATER FOLLOW-UP INSP Partial Approval SWPPP POSTED AT ENTRANCE TO SITE. NO PLAN ON SITE DUE TO VANDALISM. WILL BE KEPT AT TJ BEDNAR OFFICES.
SILT FENCE HAS BEEN RESET.
WATTLE ALONG WEST SIDE OF STOCKPILE HAS BEEN RE-STAKED
EQUIPMENT WILL BE ON SITE THIS WEEK TO ADDRESS THE SLOPE OF THE STOCKPILE AND MOVE IT BACK WITHIN THE STOCKPILE LIMITS.
01/31/2006 STORMWATER FOLLOW-UP INSP Correction Required LEFT MESSAGE AT 9:29 FOR ED CRADDOCK 349-4625.
NO WORK HAS BEEN DONE TO CORRECT ISSUES FROM 1/24 INSPECTION
AZPDES, NOI AND SWPPP HAVE NOT BEEN POSTED AS PER 12/14 INSPECTION OR AS OF 12/16 DISCUSSION WITH ED.
COMPLIANCE WITH THE STOCKPILE PERMIT AND SWPPP HAS NOT BEEN ATTAINED.
SENT NOV WITH 10 COMPLIANCE TIME FRAME OR STOP WORK ORDER WILL BE POSTED FOR THIS PERMIT AND SUBSEQUENT GRADING PERMIT T05BU01366
01/30/2006 STORMWATER FOLLOW-UP INSP Correction Required 1 DAY EXTENSION. NOV WILL BE ISSUED AS STATED IN 1/24 INSPECTION IF STORMWATER CONTROLS ARE NOT REPAIRED