Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/14/2006 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 12/04/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | SEDIMENT CONTROLS IN PLACE, SITE PARTIALLY PAVED. NO SIGNIFICANT STORM WATER CONTROLS AT THIS TIME | |
| 10/31/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | SEDIMENT CONTROLS IN PLACE, NO ACTIVITY ON SITE. NO STORM WATER CONCERNS AT THIS TIME. |
|
| 10/03/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) POST A SIGNED COPY OF YOUR NOI AT ENTRANCE TO SITE. 2) ESTABLISH A DESIGNATED CONCRETE WASH OUT ON SITE PER YOUR PLAN. 3) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT THE DURATION OF THE PROJECT. 4) SWEEP UP TRACKED MATERIAL OFF OF PUBLIC ROADS ON A ROUTINE BASIS. |