Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2007 | GRADING - FINAL | Approved | Contractor completed punch. Received letter from engineer. Per Patricia Gilbert revised grading plan was approved. | |
| 11/13/2006 | GRADING - FINAL | Not ready for Inspection | Contractor need to submit perk test for basin. | |
| 11/08/2006 | GRADING - FINAL | Partial Approval | Met with Mark site super in regards to perk test. Contractor needs to submit perk test to city engineer. | |
| 10/10/2006 | GRADING - FINAL | Partial Approval | Spoke to Patricia in regards to the perk test. Perk test needs to be complete due to past problems with the function of the basin. | |
| 08/28/2006 | GRADING - FINAL | Correction Required | Basin holding water. Contacted Mark with Chesnut to get it pumped out. | |
| 08/09/2006 | GRADING - FINAL | Correction Required | Spoke to Mark site super for Chestnut. Explained to Mark the basin was holding water for more then 24 hours and they need to complete a post perk. test. | |
| 07/11/2006 | GRADING - FINAL | Not ready for Inspection | Walked site with Bill Fisher and went over final punch list. Contractor has addressed some items. Contractor needs to address access ramp in basin. | |
| 07/10/2006 | GRADING - FINAL | Not ready for Inspection | Contractor continues to work on final punch list items. | |
| 06/02/2006 | GRADING - FINAL | Denied | Contractor needs to address: 1- Install HC ramp per city of Tucson standards. 2- Install all fencing, per site plan. 3- Complete all striping. 4- Scupper all downspouts under new sidewalk eastside existing building. 5- Have engineer address basin size. Not per approved plan. 6- Install safety barrier around basin. 7- Backfill all open holes. 8- Stabilize all area distrubed by construction activity. 9- clean parking lot. 10- Seperate all construction material from public access. 11- Provide letter from engineer in regards to drainage and basin. Per City of Tucson Standards. |