Inspection Status: Partial Approval
Inspection History: STORMWATER FOLLOW-UP INSP
| Date |
Description |
Inspector |
Results |
Comments |
| 09/08/2008 |
STORMWATER FOLLOW-UP INSP |
|
Partial Approval |
No activity on site at this time. No SWPPP issues at this time. |
| 04/14/2008 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Contractor needs to repair wattle around site. Clean washout from basin. Remove spoil material from street. Spoke to Dave site super in regards to. Dave cell- 240-3934. |
| 02/05/2008 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Contractor needs to re-install check damn at basin inlet. No activity at this time. |
| 12/07/2007 |
STORMWATER FOLLOW-UP INSP |
|
Partial Approval |
Contractor installing sewer line. Contractor needs to re-install inlet protection (rock wier) at basin inlet. This was installed to help stop flooding out existing homeowners, until basin is complete. |
| 09/04/2007 |
STORMWATER FOLLOW-UP INSP |
|
Not ready for Inspection |
Met on site with homeowner, developer, contractor and engineer. Went over concerns homeowner has with site drainage. Developer will cut basin in and install check dams. |
| 08/27/2007 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Spoke to Mark with MW2 development, site has been in-active for more then 60 days. I explained to Mark that if work does not start in the next 2 weeks, I will issue a Notice of Violation. Contractor is in violation of state permit. Site needs to be stabilized. Mark said work should start in 2 weeks and it would not be a problem. |
| 08/07/2007 |
STORMWATER FOLLOW-UP INSP |
|
Correction Required |
Received complaint call from home owner who lives on the northeast corner of project. Home owner has concerns with drainage from site. I tried to explain how the detention basin will work. Home owner was not satified, so I gave them Loren's phone number so they could speak to him. Loren is the review engineer for this site. |
| 05/21/2007 |
STORMWATER FOLLOW-UP INSP |
|
Partial Approval |
Contractor installed fence front of project. Controls in place. |