Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 12/14/2006 |
GRADING - FINAL |
|
Approved |
|
| 12/12/2006 |
GRADING - FINAL |
|
Partial Approval |
Contractor cut header wall. Contractor is ready to call in final inspection. |
| 11/20/2006 |
GRADING - FINAL |
|
Correction Required |
Contractor needs to cut both headers at outlet. To high. |
| 11/08/2006 |
GRADING - FINAL |
|
Partial Approval |
Met with owner in regards to weir installation. Contractor forming up weir. |
| 10/10/2006 |
GRADING - FINAL |
|
Partial Approval |
Met with Jim C. owner, in regards to what is required for a temp C of O. Jim will need to get a phased site plan approved by the city engineering dept. and complete all work in the phased area. Seperate all construction activity from public access. Complete all handicapped accessibility items in the phased area. |
| 01/18/2006 |
GRADING - FINAL |
|
Correction Required |
Contractor has cleared and grubbed site. No stormwater controls have been installed. Spoke to Dave site super DEC Contractors, will meet onsite 1/19/06 at 1000 hours. |
| 12/28/2005 |
GRADING - FINAL |
|
Not ready for Inspection |
Contractor has had building corners staked out. |
| 12/12/2005 |
GRADING - FINAL |
|
Not ready for Inspection |
Unchanged, no activity. |
| 11/21/2005 |
GRADING - FINAL |
|
Not ready for Inspection |
Contractor has installed temp fencing around site. No activity. |