Permit: T05BU01707

Parcel: 14027038C


Addresses:

2651 E GANLEY RD

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
12/14/2006 STORMWATER FOLLOW-UP INSP Approved All areas stabilized
10/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor starting to cut basin in. Spoke to Jim in regards to Providing phased drawing for temp C of O, stabilizing all areas disturbed by construction and submitting revised drawings for approval.
10/03/2006 STORMWATER FOLLOW-UP INSP Partial Approval Met with Jim F. on site to look at grading. Checked grade around rear of building.
10/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor removed fence, also started grading parking lot.
08/30/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time. Contractor starting to grade parking area.
08/10/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor install gravel pad to controls track out.
07/27/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to control track out.
07/10/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to contractor about installing safety barrier around open hole. (in rightway)
06/14/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor made correction noted on last inspection.
05/31/2006 STORMWATER FOLLOW-UP INSP Correction Required Put wattle back in working order. Contractor buired in various locations.
05/17/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- uncover wattle northside of project.
2- Clean dirt out of roadway, or install stormwater controls around.
Spoke to owners son in regards to issues.
05/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to:
1- install construction entrance if contractor continues to use entrance off Ganley.
2- Repair stormwater controls northeast corner of project.
Spoke to owners son in regards to issues.
04/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to watch track out.
03/29/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time.
03/02/2006 STORMWATER FOLLOW-UP INSP Correction Required Contacted owner jim in regards to black oily liquid dumped in hole on north side of project. I explained to Jim it needed to be cleaned up ASAP. Also he needs to schdule me back out when clean up starts.
02/13/2006 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time. Building pad complete.
01/19/2006 STORMWATER FOLLOW-UP INSP Correction Required Met on site with owner of site. The owner is also acting as the super for this project. This is his first attempt at construction. I went over SWPPP issues with him and also went over the SWPPP drawings. I explained SWPPP controls are are the first step. I told him if did not get them up in 14 days I would issue a correction notice which could result in a stop work order or a citation for violation of the stormwater ordinance.