Inspection History Details
Permit: T05BU01518
Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2006 | STORMWATER INSTALL OF CONTROLS | Approved | ENSURE THAT ALL INSTALLED SILT FENCE IS KEYED INTO THE GROUND AT THE BOTTOM OF THE FENCE. NO ADDITIONAL STORM WATER CONCERNS AT THIS TIME. |
|
| 03/28/2006 | STORMWATER INSTALL OF CONTROLS | Correction Required | 1) ENSURE PERIODIC SEDIMENT CONTROL MAINTENANCE AND INSPECTIONS ARE PERFORMED AND DOCUMENTED AS REQUIRED BY YOUR STORM WATER POLLUTION PREVENTION PLAN (SWPPP). 2) MOVE SILT FENCE AT INLET TO CUL-DE-SAC AS DISCUSSED IN LAST INSPECTION (3-21-06). 3) CALL IN FOR INSPECTION (#09154) AS SOON AS READY. |
|
| 03/21/2006 | STORMWATER INSTALL OF CONTROLS | Not ready for Inspection | 1) INSTALL A STABILIZED CONSTRUCTION ENTRANCE AS SHOWN ON YOUR APPROVED SWPPP. 2) REPAIR AND/OR RE-INSTALL SILT FENCE ALONG SOUTH PERIMETER. 3) MOVE SILT FENCE AT INLET TO CUL-DE-SAC FROM STREET ON EAST SIDE OF PROPERTY TO THE WEST OUTLET OF CUL-DE-SAC (COMMON AREA) 4) ENSURE THAT SILT FENCE IS KEYED INTO GROUND AT BOTTOM EDGE. |
|
| 03/07/2006 | STORMWATER INSTALL OF CONTROLS | Not ready for Inspection | NO ACTIVITY AT THIS TIME, STORM WATER CONTROLS NOT IN PLACE AS OF TODAY |