Permit: T05BU01511


Addresses:

825 W CONGRESS ST


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T05BU01511

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
10/17/2006 STORMWATER FOLLOW-UP INSP Approved Borrow pit. Closed per Elizabeth.
10/09/2006 STORMWATER FOLLOW-UP INSP Correction Required Spoke to Brent in regards to track out from Congress to the on ramp to I-10. Brent said he had a sweeper scheduled for 10:30am and at 3:30pm.
09/26/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Install temp. fence around pit #2. Per approved drawing. (safety)
2- Install SWPPP controls northwest corner.
3- Make repairs to SWPPP controls around site as needed.
4- Contractor needs to install SWPPP controls in new disturbed areas as needed.
Spoke to Brent and Gale in regards to issues, on site.
08/17/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor addressed some items from last inspection, continues to work on punch list.
08/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to:
1- Repair security fence.
2- Repair controls around catch basin northwest corner.
3- Repair gravel pad entrance.
4- Install controls northeast corner.
5- Install controls southeast corner. Around stock pile.
Spoke to site super in regards to control installation.
Per Mike with Granite connect to permit #T04BU02986
06/09/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to install concrete wash out area and ensure usage.
05/24/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Repair/replace silt fence on northwest corner. (2nd notice)
2- Install drainage channel south side of project.
Spoke to Brent site super in regards to issues. Need to watch catch basins and west side for erosion.
05/10/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Install stormwater controls around all catch basins.
2- Repair silt fence on northwest corner of project.
Spoke to Mike site super in regards to issues at approx. 1320 hours.