Permit: T05BU01366

Parcel: 13614011E


Addresses:

8200 E STELLA RD

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Date Description Inspector Results Comments
05/06/2020 GRADING - INTERMEDIATE Approved SITE APPEARS TO BE CONSTRUCTED PER THE APPROVED PLANS, NO INSPECTIONS HAVE BEEN CALLED IN SINCE 11/2007, AND NO CLOSEOUT DOCUMENTATION HAS BEEN PROVIDED BY THE ENGINEER OF RECORD FOR THIS SITE.
10/14/2008 GRADING - INTERMEDIATE Correction Required GRADING WORK IN WASH DONE-NOT BY TJ BEDNAR-REPORTS ARE THAT IT WAS COT EQUIPMENT

SEE PICTURES 3322-3330
03/05/2008 GRADING - INTERMEDIATE Partial Approval LANDSCAPE IRRIGATION BEING INSTALLED ALONG SLOPES ALONG WASH
03/05/2008 GRADING - INTERMEDIATE Partial Approval LANDSCAPING IRRIGATION BEING PLACED ALONG SLOPES ON EITHER SIDE OF WASH/DRAINAGEWAY
01/24/2008 GRADING - INTERMEDIATE Partial Approval DRIVEWAYS INSTALLED AND ROADS PAVED ON WEST SIDE OF WASH
09/04/2007 GRADING - INTERMEDIATE Partial Approval WEDGE CURB BEING INSTALLED ON EAST SIDE OF PROJECT
03/30/2007 GRADING - INTERMEDIATE Partial Approval SITE WORK CONTINUING
PER ED SCREENING WORK/OVER EX IS COMPLETE
CONTROLS HAVE BEEN MAINTAINED
03/13/2007 GRADING - INTERMEDIATE Partial Approval CHECKED ACCESS
IT HAS BEEN CLEARED FOR GARBAGE TRUCK
03/08/2007 GRADING - INTERMEDIATE Correction Required CALLED ED CRADDOCK TO ADVISE THAT SCE HAS BEEN PILED UP ON THE WEST SIDE BLOCKING ACCESS TO ALLEY WAY FOR GARBAGE TRUCKS, ETC.
03/06/2007 GRADING - INTERMEDIATE Correction Required MET WITH ED AND RUSSEL ON SITE
STOCK PILE CURRENTLY BEING MOVED
PIPE IS BEING HAULED OFF (BAGGED/PAINTED/ETC)
03/05/2007 GRADING - INTERMEDIATE Correction Required CALLED ED
STOCKPILES NOT KNOCKED DOWN
WASH XING STILL BEING USED
QUESTION ON GRADING LIMITS
SEE 2054-2057
03/05/2007 GRADING - INTERMEDIATE Correction Required STOCK PILES STILL NOT MOVED
WASH XING BEING USED FOR MOVING DEBRIS FROM BERM AREA WEST OF WASH
SCREENING WORK STILL ON GOING
03/01/2007 GRADING - INTERMEDIATE Correction Required STOCK PILES ARE TOO HIGH
CALLED AND ADVISED ED
HE IS TO HAVE THEM KNOCKED DOWN
ALSO THE WASH CROSSING IS NOT TO BE USED-ED TO BLOCK OFF THE WASH CROSSING AGAIN
02/28/2007 GRADING - INTERMEDIATE Partial Approval HAULING WORK
01/30/2007 GRADING - INTERMEDIATE Partial Approval MET ON SITE WITH LANCE PETERSON
LANCE IS TO CONTACT MANNY GRADILLAS (AREA SUPERVISOR) AND DISCUSS REMOVAL OF CONCRETE IN WASH AREA-NO PART OF TJ BEDNAR'S SCOPE AND POSSIBLE REPAIRS FOR EROSION AT WEST SIDE OF BOX CULVERT STRUCTURE
01/18/2007 GRADING - INTERMEDIATE Partial Approval SITE VISIT
SEE PICS 1949-1950
NO STORMWATER CONCERNS AT THIS TIME
01/08/2007 GRADING - INTERMEDIATE Continued MET ON SITE WITH LAITH AND ED CRADDOCK
LAITH HAS APPROVED USE OF WASH CROSSING
LOW FLOW CHANNEL MUST BE RE-ESTABLISHED AND GRADE RESET
SEE PICS 1916-1932
11/02/2006 GRADING - INTERMEDIATE Continued WATTLES ARE TO BE REPLACED 11/03

PER ED CRADDOCK:
552 TONS OF INERT HAS BEEN TRUCKED OUT
70,000 TONS OF DIRT MOVED
A SHOPPING CART WAS REMOVED FROM THE EAST SIDE OF SITE 9' DEEP
10/24/2006 GRADING - INTERMEDIATE Continued SEE PICS 1558-1574 AND WASH CROSSING
10/13/2006 GRADING - INTERMEDIATE Continued NO FURTHER TRAFFIC ACROSS WASH
10/12/2006 GRADING - INTERMEDIATE Continued TALKED TO JASON WITH YOUNG AND SONS CONTRATING
-WORK MAY RESUME ON SITE ON EAST SIDE AS LONG AS THERE IS NO TRAFFIC THROUGH WASH AREA
-GRADING LIMITS ARE TO BE RE-ESTABLISHED AND MAINTAINED UNTIL MITIGATION PLAN IS FULLY APPROVED AND SWPPP CONTROLS ARE INSTALLED PER PLAN.

SPOKE WITH LARRY SCHROEDER AND ED CRADDOCK WITH TJ BEDNAR AS WELL
10/11/2006 GRADING - INTERMEDIATE Violation POSTED STOP WORK ORDER
CROSSING IN WASH HAS BEEN CUT IN
THIS IS CONTRARY TO GRADING PLAN
STOPPED ALL WORK ON SITE
10/11/2006 GRADING - INTERMEDIATE Violation SPOKE WITH LAITH ALSHAMI
MITIGATION PLAN IS APPROVABLE WITH ARMY CORP OF ENGINEERS APPROVAL AND DEQ APPROVAL. NEEDS SUBMITTAL OF SWPPP ALSO.

PER LAITH WORK MAY RESUME ON SITE AS LONG AS NO FURTHER DISTURBANCE IN WASH