Permit: T05BU01319

Parcel: 10120040D

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
03/01/2007 GRADING - FINAL Approved PERFORMED INSPECTION OFF OF APPROVED REVISED PLAN DATED 2/22/07. FINAL GRADING IS APPROVED.
11/08/2006 GRADING - FINAL Denied COMPLETE THE FOLLOWING PRIOR TO APPROVAL:

1) PROVIDE ENGINEER CERT. THAT BASINS AND DRAINAGE WAYS HAVE BEEN COMPLETED PER APPROVED PLANS.
2) GROUT ALL STORM MAN HOLE FRAMES IN PLACE.
3) COMPLETE SIDEWALK TO RIGHT-OF-WAY AT SE CORNER.
4) CLEAN OUT STORM DRAIN LINE BETWEEN BASIN #2 AND #3.
5) PROVIDE LETTER FROM ENGINEER AND AS-BUILT ON CHANGES MADE DURING CONSTRUCTION TO THE APPROVED GRADING PLAN: BASIN #1, BASIN #3A, MAN HOLE IN DRIVE THROUGH.
6) REMOVE WADDLE LOCATED BEHIND TRASH ENCLOSURE ON NORTH SIDE.