Permit: T05BU01279

Parcel: 140260310


Addresses:

6203 S CAMPBELL AV


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T05BU01279

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
10/01/2007 STORMWATER FOLLOW-UP INSP Approved All areas stabilized.
08/01/2007 STORMWATER FOLLOW-UP INSP Correction Required No activity on site. Contractor needs to repair wier from storm and have new design approved.
06/26/2007 STORMWATER FOLLOW-UP INSP Correction Required No activity, contractor has not repaired weir.
05/11/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor striped parking lot. Forming up north side next to fence. Bike parking installed.
02/26/2007 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to site super in regards to paal on northwest and southwest side (min of 24 feet) and dumpster location. Contractor to start paving on Friday.
02/05/2007 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to John in regards to moving trash enclosure for access. Contractor grading around building.
01/09/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to clean up wash out around site. Re-install controls next to entrance. Spoke to site super in regards to.
12/13/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to:
1- Stake down wattle.
2- Provide wash out area for sub-contractors.
3- Contractor still has not contacted John Clark in regards to trash enclosures. I explained to John Waid this item will hold up C of O.
10/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to John in regards to moving wattle from west side to the east side of project. With basin cut in on west side controls no longer needed.
10/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval Site unchanged from last inspection.
09/19/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to make repairs to wattle on the north and west side. Spoke to Jon Wade in regards to via cell phone.
08/10/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor started installing basin pipeing.
08/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor completed trench, will back fill bottom of pipe zone with 3/4" to 1" drain rock.
07/27/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to repair silt fence and wattle on west side of project.
07/10/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor stock piling material on site no stormwater controls installed.
04/18/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.
03/29/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity
03/14/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity
03/03/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.
01/18/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.