Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
Permit Number - T05BU00812
Inspection Description - GRADING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/05/2009 | GRADING - INTERMEDIATE | Approved | ||
03/03/2008 | GRADING - INTERMEDIATE | Partial Approval | SITE IS COMPLETELY BUILT OUT NO REQUEST FOR FINAL GRADING NO BASIN CERTIFICATIONS HAVE BEEN RECEIVED |
|
07/23/2007 | GRADING - INTERMEDIATE | Partial Approval | NO STANDING WATER IN CHANNELS AT THIS TIME SITE APPEARS TO BE DRAINING |
|
06/12/2007 | GRADING - INTERMEDIATE | Correction Required | MET WITH MALENA ON SITE TALKED TO JIM 488-8606 SITE SUPER REGARDING LOTS 76-85 (W SIDE OF GUPTA) BEING GRADED TO DRAIN TO FRONT PLAN CALLS FOR REAR DRAINAGE ALSO TALKED ABOUT LOT 197-RIP RAP IS TO BE GROUTED ON S SID OF LOT ALONG JUMPING CHOLLA EAST SIDE OF PARK IS 2:1/2.5:1 AND HAS BEEN STABILIZED WITH DG. THE SLOPE NEEDS TO BE FEATHERED TO 3:1 OR ALTERNATE STABILIZATION NEEDS TO BE USED TALKED TO SAM WITH LDA 609-8936 AND WAS REFERRED TO AARON WITH DR HORTON LAND DEV 488-6111 |
|
12/28/2006 | GRADING - INTERMEDIATE | Correction Required | CORRECTION NOTICE 7 DAYS -TRADES PARKING ON LOTS 154, 148, 147, 186, 191 -WASHOUT LOT 160 -LOT 126 DIRT RAMP OVER SIDEWALK INTO STREET |
|
07/12/2006 | GRADING - INTERMEDIATE | Partial Approval | DRAINAGE WAY WORK HAS STARTED SITE NEEDS TO BE SWEPT 2ND CONCRETE WASHOUT?? |
|
06/28/2006 | GRADING - INTERMEDIATE | Correction Required | Nichole, The schedule for the drainge channel at Empire Heights is as follows. 6-29-06 Remove existing rip rap 6-30-06 Staking 7-5-06 grading of slopes and channel floor (10 days) 7-17-06 installation of gunite and retaining wall (15 days) Please feel free to give me a call if you have any questions. My cell number is (520) 331-5329 Thank you, Ben Myers Project Manager-Arizona Underground. I HAVE EMAILED THIS SCHEDULE TO ANDREA MARAFINO THIS PUTS THE WORK WELL INTO HISTORICAL MONSOON. DR HORTON WILL BE RESPONSIBLE FOR CLEANING THE DRAINAGEWAY AT THE END OF THE PROJECT/WHEN THE SITE IS STABLE |
|
06/14/2006 | GRADING - INTERMEDIATE | Correction Required | TALKED TO ANDREA MARAFINO REGARDING SCHEDULE FOR DRAINAGEWAY SHE IS TO GET PM TO CONTACT ME. | |
05/16/2006 | GRADING - INTERMEDIATE | Correction Required | MET ON SITE WITH PM CONSTRUCTION SCHEDULE FOR DRAINAGEWAY SHOULD BE FORTH COMING ANDREA MARAFINO IS AWARE A BACK UP PLAN FOR SWPPP NEEDS TO BE IN PLACE FOR CONSTRUCTION CONTROLS |
|
05/08/2006 | GRADING - INTERMEDIATE | Correction Required | SPOKE WITH ANDREA MARAFINO THE UNFINISHED DRAINAGE WAY MUST BE ADDRESSED FOR SWPPP (BY ENGINEER) BEFORE MONSOON |
|
03/23/2006 | GRADING - INTERMEDIATE | Partial Approval | MET WITH DAN DESSENT ON SITE FROM DR HORTON PLANS HAVE BEEN GIVEN TO PAUL MACHADO FOR THE DRAINAGE WAY-THERE HAS BEEN NO APPROVAL AT THIS TIME |
|
03/17/2006 | GRADING - INTERMEDIATE | Partial Approval | SPOKE TO MR. SULLIVAN AND GAVE HIM PDEQ # FOR THE DUST CONCERNS. IN FURTHER DISCUSSION I WAS TOLD AZ UG IS PARKING THEIR EQUIPMENT NEXT TO THE SUBDIVISION WALL AND THE LUBE TRUCKS SERVICING THE EQUIPMENT ARE DISTURBING THE HOMEOWNERS AFTER HOURS. SPOKE TO MARK WITH AZ UG 247-3627 (UG FOREMAN) WE DISCUSSED THE BENEFIT OF BEING A BETTER NEIGHBOR AND MADE HIM AWARE OF THE ISSUES WITH THE LUBE TRUCKS. MARK SAID HE WOULD MAKE A CONCERTED EFFORT TO KEEP THE SITE WATERED AND MAKE SURE THE EQUIPMENT IS PARKED IN SUCH A MANNER THAT THE LUBE TRUCKS WILL NO LONGER SHINE THEIR LIGHTS INTO THE RESIDENTIAL AREA IN ORDER TO PERFORM MAINT. I RECEIVED A FOLLOW UP PHONE CALL FROM MRS. SULLIVAN. THEY WILL KEEP ME APPRISED OF ANY CHANGES IN THE SITUATION, FOR THE BETTER OR THE WORSE. |
|
02/23/2006 | GRADING - INTERMEDIATE | Partial Approval | SPOKE WITH UNDERGROUND FOREMAN HE IS AWARE THERE ARE NO APPROVED PLANS FOR DRAINAGEWAY. HE IS ALSO AWARE THAT NO WORK IS TO BE DONE ON THE DRAINAGEWAY UNTIL APPROVED PLANS ARE ON SITE. HE WILL ADVISE SITE SUPER AND GIVE HIM ANOTHER BUSINESS CARD. |
|
02/21/2006 | GRADING - INTERMEDIATE | Partial Approval | NO WORK ON DRAINAGE WAY STILL NO CALL FROM SITE SUPER/ENGINEER/PM RE DESIGN FOR DRAINAGE WAY |
|
02/10/2006 | GRADING - INTERMEDIATE | Partial Approval | SPOKE TO JOE RIOJAS AT EEC 321-4625. THE STRUCTURAL DESIGN FOR THE DRAINAGEWAY WAS TO HAVE BEEN DONE BY ANOTHER ENGINEER. DAN DESENT WITH DR HORTON WAS MADE AWARE OF THE PERMITING PROCESS. I WILL CALL TO SEE WHERE THE PLANS ARE FOR THE TIE-IN FOR THE EXISTING DRAINAGEWAY. | |
02/08/2006 | GRADING - INTERMEDIATE | Partial Approval | SPOKE TO LAURA LEE 742-5674 XTN 15 WITH LEWIS MGMT CO. SHE HAD CONCERNS FROM DESERT CROSSING HOA REGARDING THE DESIGN OF THE DRAINAGEWAY. SEE ATTACHED PICTURES OF BUILD STATUS. I ASSURED HER IT WAS REVIEWED BY COT DSD ENG. (PAUL MACHADO) |