Permit: T05BU00812

Parcel: 14117012B

Inspection Status: Approved

Inspection History: GRADING - INTERMEDIATE

Permit Number - T05BU00812

Inspection Description - GRADING - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
05/05/2009 GRADING - INTERMEDIATE Approved
03/03/2008 GRADING - INTERMEDIATE Partial Approval SITE IS COMPLETELY BUILT OUT
NO REQUEST FOR FINAL GRADING
NO BASIN CERTIFICATIONS HAVE BEEN RECEIVED
07/23/2007 GRADING - INTERMEDIATE Partial Approval NO STANDING WATER IN CHANNELS AT THIS TIME
SITE APPEARS TO BE DRAINING
06/12/2007 GRADING - INTERMEDIATE Correction Required MET WITH MALENA ON SITE
TALKED TO JIM 488-8606 SITE SUPER REGARDING LOTS 76-85 (W SIDE OF GUPTA) BEING GRADED TO DRAIN TO FRONT PLAN CALLS FOR REAR DRAINAGE

ALSO TALKED ABOUT LOT 197-RIP RAP IS TO BE GROUTED ON S SID OF LOT ALONG JUMPING CHOLLA

EAST SIDE OF PARK IS 2:1/2.5:1 AND HAS BEEN STABILIZED WITH DG. THE SLOPE NEEDS TO BE FEATHERED TO 3:1 OR ALTERNATE STABILIZATION NEEDS TO BE USED
TALKED TO SAM WITH LDA 609-8936 AND WAS REFERRED TO AARON WITH DR HORTON LAND DEV 488-6111
12/28/2006 GRADING - INTERMEDIATE Correction Required CORRECTION NOTICE 7 DAYS
-TRADES PARKING ON LOTS 154, 148, 147, 186, 191
-WASHOUT LOT 160
-LOT 126 DIRT RAMP OVER SIDEWALK INTO STREET
07/12/2006 GRADING - INTERMEDIATE Partial Approval DRAINAGE WAY WORK HAS STARTED
SITE NEEDS TO BE SWEPT
2ND CONCRETE WASHOUT??
06/28/2006 GRADING - INTERMEDIATE Correction Required Nichole,
The schedule for the drainge channel at Empire Heights is as follows.

6-29-06 Remove existing rip rap
6-30-06 Staking
7-5-06 grading of slopes and channel floor (10 days)
7-17-06 installation of gunite and retaining wall (15 days)

Please feel free to give me a call if you have any questions. My cell number
is (520) 331-5329

Thank you,
Ben Myers
Project Manager-Arizona Underground.

I HAVE EMAILED THIS SCHEDULE TO ANDREA MARAFINO
THIS PUTS THE WORK WELL INTO HISTORICAL MONSOON. DR HORTON WILL BE RESPONSIBLE FOR CLEANING THE DRAINAGEWAY AT THE END OF THE PROJECT/WHEN THE SITE IS STABLE
06/14/2006 GRADING - INTERMEDIATE Correction Required TALKED TO ANDREA MARAFINO REGARDING SCHEDULE FOR DRAINAGEWAY SHE IS TO GET PM TO CONTACT ME.
05/16/2006 GRADING - INTERMEDIATE Correction Required MET ON SITE WITH PM
CONSTRUCTION SCHEDULE FOR DRAINAGEWAY SHOULD BE FORTH COMING
ANDREA MARAFINO IS AWARE A BACK UP PLAN FOR SWPPP NEEDS TO BE IN PLACE FOR CONSTRUCTION CONTROLS
05/08/2006 GRADING - INTERMEDIATE Correction Required SPOKE WITH ANDREA MARAFINO
THE UNFINISHED DRAINAGE WAY MUST BE ADDRESSED FOR SWPPP (BY ENGINEER) BEFORE MONSOON
03/23/2006 GRADING - INTERMEDIATE Partial Approval MET WITH DAN DESSENT ON SITE FROM DR HORTON
PLANS HAVE BEEN GIVEN TO PAUL MACHADO FOR THE DRAINAGE WAY-THERE HAS BEEN NO APPROVAL AT THIS TIME
03/17/2006 GRADING - INTERMEDIATE Partial Approval SPOKE TO MR. SULLIVAN AND GAVE HIM PDEQ # FOR THE DUST CONCERNS. IN FURTHER DISCUSSION I WAS TOLD AZ UG IS PARKING THEIR EQUIPMENT NEXT TO THE SUBDIVISION WALL AND THE LUBE TRUCKS SERVICING THE EQUIPMENT ARE DISTURBING THE HOMEOWNERS AFTER HOURS.
SPOKE TO MARK WITH AZ UG 247-3627 (UG FOREMAN) WE DISCUSSED THE BENEFIT OF BEING A BETTER NEIGHBOR AND MADE HIM AWARE OF THE ISSUES WITH THE LUBE TRUCKS. MARK SAID HE WOULD MAKE A CONCERTED EFFORT TO KEEP THE SITE WATERED AND MAKE SURE THE EQUIPMENT IS PARKED IN SUCH A MANNER THAT THE LUBE TRUCKS WILL NO LONGER SHINE THEIR LIGHTS INTO THE RESIDENTIAL AREA IN ORDER TO PERFORM MAINT.
I RECEIVED A FOLLOW UP PHONE CALL FROM MRS. SULLIVAN. THEY WILL KEEP ME APPRISED OF ANY CHANGES IN THE SITUATION, FOR THE BETTER OR THE WORSE.
02/23/2006 GRADING - INTERMEDIATE Partial Approval SPOKE WITH UNDERGROUND FOREMAN
HE IS AWARE THERE ARE NO APPROVED PLANS FOR DRAINAGEWAY. HE IS ALSO AWARE THAT NO WORK IS TO BE DONE ON THE DRAINAGEWAY UNTIL APPROVED PLANS ARE ON SITE. HE WILL ADVISE SITE SUPER AND GIVE HIM ANOTHER BUSINESS CARD.
02/21/2006 GRADING - INTERMEDIATE Partial Approval NO WORK ON DRAINAGE WAY
STILL NO CALL FROM SITE SUPER/ENGINEER/PM RE DESIGN FOR DRAINAGE WAY
02/10/2006 GRADING - INTERMEDIATE Partial Approval SPOKE TO JOE RIOJAS AT EEC 321-4625. THE STRUCTURAL DESIGN FOR THE DRAINAGEWAY WAS TO HAVE BEEN DONE BY ANOTHER ENGINEER. DAN DESENT WITH DR HORTON WAS MADE AWARE OF THE PERMITING PROCESS. I WILL CALL TO SEE WHERE THE PLANS ARE FOR THE TIE-IN FOR THE EXISTING DRAINAGEWAY.
02/08/2006 GRADING - INTERMEDIATE Partial Approval SPOKE TO LAURA LEE 742-5674 XTN 15 WITH LEWIS MGMT CO.

SHE HAD CONCERNS FROM DESERT CROSSING HOA REGARDING THE DESIGN OF THE DRAINAGEWAY. SEE ATTACHED PICTURES OF BUILD STATUS. I ASSURED HER IT WAS REVIEWED BY COT DSD ENG. (PAUL MACHADO)