Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T05BU00810
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/24/2009 | STORMWATER FOLLOW-UP INSP | Approved | ||
12/07/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor installed railing a long road. | |
06/14/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No concerns at this time. | |
05/31/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No stormwater concerns at this time. | |
05/17/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No stormwater concerns at this time. Contractor still needs to install handrail and gaurdrail. | |
05/02/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No stormwater concerns at this time. Contractor still needs to install handrail and guardrail. | |
04/19/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No stormwater concerns in regards to box culvert. | |
03/30/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No stormwater concerns at this time. | |
03/16/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No concerns at this time. Controls in place. | |
03/09/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor installed controls at box inlet. | |
02/16/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Spoke to Adrea in regards to installing controls around box culvert. | |
02/02/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor finished rip rap work around box culvert. Contractor still needs to install stormwater controls in inlet. |
|
01/19/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor has a small amout of rip rap rock work to do. Spoke to Andrea in regards to cleaning silt out of the box culvert and installing controls to keep silt from building up inside the box culvert and around inlet/outlet. | |
01/04/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor installing rip rap and filter fabric. | |
12/14/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor removing silt and completeing fine grading around box culvert. | |
11/23/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor given copy of Stormwater Ordinance. No concerns at this time. |
|
11/09/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor paved entrance off of Campbell. | |
10/25/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor installed waddle noted on last inspection. Contractor has started to use the entrance on Campbell. No construction entrance has been installed. Contractor wants to keep track-out clean leaving site. |
|
10/11/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to install stormwater controls on northside of access road to controls silt. (access road ties into Cambell) | |
09/27/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to to install waddle along road from box culvert to to Campbell. | |
09/14/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Met on site with contractor and went over stormwater controls issues. At 1000 hours. Contractor will address installing waddle or silt fence to control silt. West of box culvert. Contractor to address issues and schedule re-inspection. |
|
07/19/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor forming up deck of box culvert. Per AZ Dept. of Highway Standard drawing B-02.40 | |
07/13/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Talk to concrete formen in regards to grouting cone holes on out side walls of box culvert. He said sould not be a problem. | |
07/07/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Reber install in vertical walls per shop drawing on site. Concrete and Rebar special inspection still need to be completed. | |
06/29/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Inspected footing and rebar. Footings and rebar installed per shop drawing on site. |