Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T05BU00686
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/26/2007 | STORMWATER FOLLOW-UP INSP | Approved | SITE IS STABILIZED, ALL PAVING AND PERMANENT STORM WATER CONTROLS IN PLACE. AWAITING FINAL GRADING INSPECTION REQUEST. | |
| 12/21/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT CHANGES FROM LAST INSPECTION. | |
| 11/20/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME | |
| 11/08/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | SWEEP UP TRACKED MATERIAL, PAVING BEING ACCOMPLISHED. PROVIDE APPROVED REVISION OF ANY SIGNIFICANT CHANGES MADE TO THE APPROVED PLANS. |
|
| 09/12/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT STORM WATER ISSUES AT THIS TIME - PERIMETER OF SITE IS STABILIZED. PRIOR TO APPROVAL FROM ENGINEERING FOR A C OF O, COMPLETE THE FOLLOWING: 1) ALL SITE WORK ASSOCIATED WITH THE APPROVED GRADING/SITE PLAN. 2) ALL PARKING, TRASH ENCLOSURES, CURB RAMPS, SIDEWALKS....... 3) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT THE RET/DET BASIN WAS BUILT IAW THE APPROVED PLANS. 4) A COMPLETED AN APPROVED FINAL GRADING INSPECTION FOR PERMIT # T05BU00686. |
|
| 07/27/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO STORM WATER CONCERNS AT THIS TIME | |
| 07/14/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO STROM WATER CONCERNS AT THIS TIME. | |
| 06/14/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | 1) CALL FOR INSPECTION WHEN SITE IS PAVED/CALL FOR INTERMEDIATE GRADING INSPECTION. 2) PRIOR TO APPROVAL FOR C OF O BY ENGINEERING: A) COMPLETE SITE WORK PER APPROVED PLAN. B) PROVIDE A RET/DET BASIN CERTIFICATION STATEMENT BY THE ENGINEER OF RECORD. C) CALL FOR FINAL GRADING INSPECTION |
|
| 04/21/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. WORK SOIL IN FRONT OF WALL ALONG EAST SIDE OF SITE AS SOON AS POSSIBLE. ANY SIGNIFICANT CHANGE TO THE APPROVED GRADING PLAN MUST BE REVIEWED AND APPROVED. CALL PRIOR TO PROJECT OCCUPANCY DATE SO THAT AN INSPECTION CAN BE ACCOMPLISHED AND ANY PROBLEMS CAN BE ADDRESSED. |
|
| 02/27/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | 1) RE-ESTABLISH SEDIMENT CONTROLS (SILT FENCE) ALONG THE WEST BOUNDRY TO PROPERTY - ENSURE BOTTOM OF FENCE IS TIED INTO THE GROUND. 2) DISPOSE OF EXCESS CONCRETE AND MATERIALS PROPERLY, PROVIDE A DESIGNATED CONCRETE WASH OUT AREA. 3) SEDIMENT CONTROLS ARE REQUIRED TO REMAIN IN PLACE UNTIL ALL CURBING IS INSTALLED AND THE SITE IS STABILIZED. |
|
| 01/12/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | 1) ENSURE SEDIMENT CONTROLS LOCATED ON THE WEST SIDE OF PROPERTY IS MAINTAINED PERIODICALLY. TRENCH OR KEY IN BOTTOM OF FENCE. 2) ENSURE ROUTINE SEDIMENT CONTROL MAINT INSPECTIONS ARE PRFORMED IN ACCORDANCE WITH YOUR SWPPP. 3) ESTABLISH A DESIGNATED CONCRETE WASH OUT PER YOUR PLAN AND USE IT WHEN NECESSARY. CALL FOR REINSPECTION IF PROBLEMS OR QUESTIONS ARISE. |
|
| 12/01/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | 1) SEDIMENT CONTROLS ARE IN PLACE IN ACCORDANCE WITH THE APPROVED SWPPP. 2) ENSURE PERIODIC MAINT INSPECTIONS ARE PERFORMED AND DOCUMENTED. NO ADDITIONAL STORM WATER CONCERNS AT THIS TIME. |