Permit: T05BU00351

Parcel: 14024061E


Addresses:

1445 E WIEDING RD

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
01/19/2007 STORMWATER FOLLOW-UP INSP Approved Contractor stabilized all areas.
10/04/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Clean mason wash out from basin.
2- Address erosion eastside of building.
3- Stabilize area around trash enclosure.
4- Contractor still needs to regrade so stormwater flows into the basin.
Spoke to Gregg in regards to issues.
08/29/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to clean and install stormwater controls on the northwest side of project. Spoke to site super in reagrds to issues.
08/11/2006 STORMWATER FOLLOW-UP INSP Partial Approval 1- Basin on north side holding water for more then 24 hours. Post perk test required before C of O.
2- Contractor needs to continue to keep streets clean.
Spoke to Gregg site super in regards to via cell phone.
08/08/2006 STORMWATER FOLLOW-UP INSP Partial Approval Met on site with Gregg site super. Went over west side slope bank. Owner wants to install planters and leave plants in. Also will need to install trucated domes. Contractor wants to change basin on east side of building. I told contractor he will need to have all changes to basin approved at 201 N. Stone.
08/01/2006 STORMWATER FOLLOW-UP INSP Correction Required Clean parking lot westside of project. Contractor needs to install controls along westside of project.
07/18/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to install controls around or remove stock pile. Spoke to Gregg via cell phone in regards to.
06/15/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to install controls around stock pile. Spoke to Gregg new site super
06/01/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to keep track out cleaned up on Rens rd. Left message for Gregg (481-3569) in regards to issue, never called back.
05/17/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to site super in regards to:
1- Cleaning Rens Rd. (runoff from basin work, may needs controls)
2- Baqnk slope on eastside basin is 1.5 to 1. May need grouted rip rap.
3- Provide concrete wash out area.
05/05/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor washed down the street. I contacted Amy site super (603-5318) and explained that streets can not be wash down. Streets will need to be sweeped unless thier going to install stormwater controls down Wieding Rd.
05/03/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to control track out from site. Spoke to Mike Gillis at 0845 hours. Mike said he would call the site super and get things cleaned up.
04/20/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time.
04/04/2006 STORMWATER FOLLOW-UP INSP Partial Approval Keep streets clean. Spoke to John site super at approx. 1030. via cell phone in regards to streets.
03/16/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to keep street clean.
02/16/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.
02/03/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.
01/19/2006 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.
12/14/2005 STORMWATER FOLLOW-UP INSP Not ready for Inspection No activity.