Permit: T05BU00164


Addresses:

6300 S ALVERNON WY


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T05BU00164

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
12/29/2008 STORMWATER FOLLOW-UP INSP Approved All ares stablilzed.
07/02/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor continues to clean drainage channel. Contractor has not installed SWPPP controls.
06/26/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor running equipment in drainage channel. Met Ron A. on site explained to Ron they can cut the vegatation, but if they are going to use equipment the channel will need to be stabilize when work is completed. Contractror will need to install SWPPP controls. Ron said he understood. Contractor is working outside grading limits.
02/02/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to call in final grading inspection.
01/08/2007 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Sweep Desert Range Ct.
2- Clean wash out from lots 33 and 30.
12/12/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Keep wash out cleaned up.
2- Clean Hemispere and address material dumped off site.
Spoke to Dennis in regards to items. Dennis told me it was the landscapers who dumped to soil off site. Dennis said he will have it cleaned up ASAP.
10/19/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to clean wash out on Bright View and Sun View. Provide stucco contractor wash out area. This is the 4th. correction in the last 4 inspections. I explained to Dennis site super, that if the site is not cleaned by my next inspection I will issue a Stop Work Order until it is clean.
10/02/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Clean sidewalk infront of 6434 Sunrise Valley.
2- Clean and repair concrete wash out. (leaking)
3- Address stucco and drywall wash out around site. (no controls used)
4- Clean drywall/concrete wash out in street front of 3865 Sun View Ct.
5- Clean street (bright Sun Ave) Drywall wash out ran down curb line.
Spoke to Site super in regards to.
08/28/2006 STORMWATER FOLLOW-UP INSP Correction Required Issued Correction Notice. Contractor needs to address:
1- Clean drywall wash out from lots being constructed.
2- Remove sand from street.
3- Clean stucco wash out. Lot 91.
4- Repair concrete wash out area.
Contractor given 3 days to address items. If not complete contractor will receive SWO or NOV. Spoke to Lori site super in regards to issues.
07/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to address erosion in drainage channel southwest corner of project.
07/17/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address:
1- Address erosion in channel southwest corner.
2- Clean concrete drainage channel.
3- Repair concrete wash out.
4- Repair wattle around detention basin.
5- Keep paint wash out cleaned up.
6- Clean wash out on Transcon Way. Next to lot 91.
Spoke to site super in regards to issues. (fill in super)
06/13/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to keep streets clean.
05/30/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to super in regards to wash out.
05/15/2006 STORMWATER FOLLOW-UP INSP Partial Approval Keep streets clean. Clean up concrete wash out.
05/01/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to keep streets clean.
04/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time. Contractor wants to watch track out.
03/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor addressed items for last inspection. Contractor needs to get spoils piles out of street.
03/16/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address:
1- Install controls around detention basin.
2- Repair controls in drainage channel on southwest corner of project.
Contacted Bob with K.B. Homes in regards to issues.
03/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to Bob with K.B. Homes in regards to:
1- Stabilizing area behind homes that back up to Valencia. Bob said the land department was going to do this at a later date. SWC will stay in place until then.
2- Install controls around detention basin. Bob is get a crew out to take care of this.
3- Silt fence needing repairson south side of project. Bob said crew would be out before the end of the week to fix this problem.
02/13/2006 STORMWATER FOLLOW-UP INSP Partial Approval No concerns. Some small track-out from house lots.
01/30/2006 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time.
01/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to James Boston with K.B. Homes. K.B. Homes to landscape all areas disturbed by construction activity, along Alvernon and Valencia.
12/28/2005 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to James Boston about area behind fence line that backs up to Velencia and Alvernon. Approx. 30' behind fence has been disturbed by construction traffic and will need to be stabilized. James to check landscaping drawings and get back to me.
12/12/2005 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time.
11/21/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address:
1- Stormwater controls down southeast side of project.
2- Stormwater controls taken down southwest side of project for concrete pipe. Contrator needs to install temp controls for work in drainage channel.
2nd. Notice.
Spoke to Dennis site super for K.B. Homes. At 0915 in regards to items.
11/07/2005 STORMWATER FOLLOW-UP INSP Correction Required Contacted Bob with K.B. homes in regards to:
1- Stormwater controls knocked down southeast side of project.
2- Stormwater controls taken down southwest side of project. Contractor needs to install temp controls for work in drainage channel.
Met Bob on site at 1330 hours. Gave Bob copy of Stromwater Ordinance.
10/24/2005 STORMWATER FOLLOW-UP INSP Partial Approval Sand bags starting to break open. Also silt in roadway. This needs to be attained to by next inspection. Call Bob with K.B. Homes in regards to issues.
10/10/2005 STORMWATER FOLLOW-UP INSP Partial Approval Silt fence in good condition. Contractor continues to work on track-out. Contractor starting to build block perimeter wall.
09/26/2005 STORMWATER FOLLOW-UP INSP Partial Approval Silt fence in good condition. Contractor making effort on track-out.
09/12/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor continues to clean track-out.
I spoke to Dennis the site super in regards to cleaning up silt in front of 6426 Sunrise Valley Dr. Dennis said he would take care of it.
08/26/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to control track-out on phases II and III.
Spoke to Bob with KB Homes in regards to this matter. Via cell phone at approx. 1050 hours.