Inspection History Details
Inspection Status: Violation
Inspection History: FOLLOW UP CODE VIOLATION
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2005 | FOLLOW UP CODE VIOLATION | Violation | NO INSPECTIONS SINCE 5-27-05 F.U. 60 DAYS |
|
| 05/27/2005 | FOLLOW UP CODE VIOLATION | Violation | 5/27/5 - PROGRESS ON INSP MADE - LAST INSP APPROVED SHEET ROCK NAILING BY D QUINN ON 5/6/5 FU 30 DAYS | |
| 03/29/2005 | FOLLOW UP CODE VIOLATION | Violation | PERMIT WAS ISSUED FOR DEMO & REBUILD. PERMIT # T05CM00519-ISSUED ON 3/25/05 & EXPIRES ON 9/21/05. DEMO PERMIT # T05BU00099-ISSUED ON 1/19/05-EXPIRES ON 7/18/05. F/U IN 60 DAYS | |
| 03/01/2005 | FOLLOW UP CODE VIOLATION | Violation | 2/24/5 - UNIT IS BEING REBUILT FU 30 DAYS. | |
| 01/27/2005 | FOLLOW UP CODE VIOLATION | Violation | PERMIT APPLIED FOR 1/14/5 FOR DEMOLITION FU 30 DAYS | |
| 12/13/2004 | FOLLOW UP CODE VIOLATION | Violation | 12/07/04 - UNIT IS SECURED BY 6' CYCLONE FENCING WITH BARBED WIRE ON TOP F/U IN 45 DAYS |