Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/17/2005 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* |
| 11/19/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*/1)SEWER PIPING BETWEEN MH #2 & #3 -#3 & #4 LOW PRESSURE AIR TEST OK |
| 11/17/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*/1)LOW PRESSURE AIR TEST BETWEEN MANHOLES #7 & #8 OK |
| 11/16/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*/1)LOW PRESSURE AIR TEST BETWEEN MANHOLE #1 & #5 - OK. 2)TEST FROM MANHOLE #5 & #6 OK. 3)ONE SECTION BETWEEN MANHOLE #6 & #7 TEST WAIVED. 4)TEST FROM MANHOLE #6 & #9 - OK. |
| 11/02/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*/1)NEW MH #4, #3, #2 TO BE VACUUM TESTED, WITH LOW PRESSURE AIR TEST ON THESE SECTIONS OF PIPE 2)223' OF NEW SEWER, PASSING THROUGH MH #2, PAST EXISTING MH #4 AND ON TO MH #1 OK TO REMAIN AS IT IS LIVE. SHOT INVERTS WITH CONTRACTOR-CLOSE ENOUGH TO PLAN. INSPECTOR WILL WAIVE TESTING ON THESE SECTIONS ONLY. |
| 10/27/2004 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :*/1)PLEASE HAVE TRANSIT READY AND MEASUREMENTS TAKEN |
| 10/26/2004 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :*/1)CALLED ON ACCOUNT OF RAIN |
| 10/21/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*/ 1) MANHOLE BASES #7, 6, 8 AND 9 OK |
| 10/14/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*/MH #1, #5, #6, #7, #8 & #9 WITH BRANCHES OK TO COVER SUBJ. TO TEST |