Permit: T04PL01629

Parcel: 14113017A


Addresses:

9314 E RITA RD


Inspection Status: Approved

Inspection History: PLUMBING - SEWER HCS CONNECT

Permit Number - T04PL01629

Inspection Description - PLUMBING - SEWER HCS CONNECT

Inspection Status - Approved

Date Description Inspector Results Comments
08/11/2005 PLUMBING - SEWER HCS CONNECT Approved IVRS - Inspection :*
1) TURNED IN PIMA COUNTY DEPT. OF ENVIORMENTAL QUALITY APPROVAL OF CONSTRUCTION (SEWER)
09/28/2004 PLUMBING - SEWER HCS CONNECT Partial Approval IVRS - Inspection :*/MANHOLE #1 VACUUM TEST OK.
09/22/2004 PLUMBING - SEWER HCS CONNECT Denied IVRS - Inspection :
See detailed listing on site.| 999*/MANHOLE #1 FAILED VACUUM TEST
09/21/2004 PLUMBING - SEWER HCS CONNECT Partial Approval IVRS - Inspection :* MANHOLE # 3 TO MANHOLE # 4 INCLUDING 4" LATERAL THRU HCS INTO BUILDING FOR FUTURE ? INTO 9356 RITA RD 5 PSI AIR TEST OK
MANHOLE # 2 VACUUM TEST OK
MANHOLE # 3 VACUUM TEST OK
MANHOLE #4 VACUUM TEST OK
MANHOLE # 5 VACUUM TEST OK
1) MANHOLE #1 VACUUM TEST AT LATER DATE.
09/20/2004 PLUMBING - SEWER HCS CONNECT Partial Approval IVRS - Inspection :*/ 1) MANHOLE #3 TO MANHOLE #5 INCLUDING 2) 4" LATERALS THRU HCS CONNECTION, THRU 2-WAY CLEANOUTS INTO BLDG FOR FUTURE 5 PSI AIR TEST OK 2) MANHOLE #3 TO MANHOLE #4 INCLUDING (1) 4" LATERAL THRU HCS CONNECTION, THRU 2-WAY CLEANOUT 5' INTO BLDG FOR FUTURE 5 PSI AIR TEST (WILL NOT HOLD TEST). MANHOLE #4 4" SEWER TO HCS THRU 2-WAY CLEANOUT 5' INTO BLDG FOR FUTURE 5 PSI AIR TEST OK
09/16/2004 PLUMBING - SEWER HCS CONNECT Partial Approval IVRS - Inspection :* 4" DUCTILE IRON INSTALLED PER PC/COT DETAIL WWM-108 IN (4) LOCATIONS PER PLAN. 1) NEED AIR TEST ON PIPING INCLUDING HCS CONNECTION FROM MANHOLE #3 TO #4, MANHOLE #4 THRU HCS CONNECTION AT 9356 E. RITA RD, FROM MANHOLE #3 TO MANHOLE #5 INCLUDING ( 2) HCS CONNECTIONS TO 9348 E. RITA RD. 2) NEED VERIFICATION OF GRADE ON ENTIRE SEWER. 3) NEED PIMA COUNTY CERTIFICATE OF CONFORMANCE FOR SEWER. 4) NEED VACUUM TEST ON MANHOLES. 5) NEED LETTER FROM ENGINEER STATING CORRECT CROSSING OF SEWER & WATER ON WEST SIDE OF PROJECT.