Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2004 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :*/CORRECTIONS HAVE BEEN MADE. REPAIRS MADE BY DARON PLUMBING. LEFT GAS CARD | |
| 09/09/2004 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 09/08/2004 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999*/1)EXTENT THE GAS LINE DOWN TO THE WATER HEATER CONNECTION. 2)PROVIDE MIN 1" CLEARANCE FROM COMBUSTIBLES AROUND WATER HEATER VENT 3)CENTER THE DRAFT DIVERTER ON THE WATER HEATER OVER THE OUTLET. 4) 60 LB. TEST GAUGE NOT ACCURATE. USE A GUAGE NOT EXCEEDING 30PSI. 5)PROVIDE A ROOF JACK WHERE WATER HEATER VENT PENETRATES THE ROOF. 6) ISOLATE THE RETURN AIR PLENUM FROM THE FURANCE CLOSET. 7)CLAMP GAS LINE ON ROOF TO BLOCKS. 8)ADD ANOTHER BLOCK NEAR WATER HEATER PENETRATION AT WALL ON ROOF.9)PROVIDE VERIFICATION THAT A LICENSED CONTRACTOR DID THE WORK. |
|
| 08/12/2004 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :*/ 1) NOT INSTALLED PER APPROVED PLAN SEE 3/4 TO FURNACE 2) PROVIDE PROPER VENTS AND VENT CAP AT FURNACE AND WATEE HEATER COMPLETE ALL GAS LINES. PROVIDE VALVES AND FLEX AT FIXTURE AT TIME OF INSPECTION. NOTE: YOU WILL NEED DBL WALL VENT THRU ROOF WITH APPROVED VENT CAP. SINGLE WALL VENT 6" CLEARANCE FROM COMBUSTIBLES. RENT UNIT PLUMBING CONTRACTOR REQUIRED |