Inspection Status: Approved
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 02/04/2004 |
PLUMBING - PROGRESS |
|
Approved |
IVRS - Inspection 0000*/ AIR PRESSURE TEST ON ENTIRE SITE SEWER SYSTEM IS OK. |
| 01/26/2004 |
PLUMBING - PROGRESS |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) SITE SEWER FROM M.H. 1 TO LOTS 1-11 AND 17-19 ONLY, AS NOTED ON PLAN. 2) OK TO BACKFILL TRENCH. 3) WILL REQUIRE A CERTIFIED SURVEYOR TO VERIFY GRADE AT EVERY 50' INTERVALS PRIOR TO BACKFILL. 4) WILL PROVIDE AN AIR PRESSURE TEST AT A LATTER TIME. |
| 01/22/2004 |
PLUMBING - PROGRESS |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ NOT READY DUE TO RAIN. |
| 01/20/2004 |
PLUMBING - PROGRESS |
|
Denied |
IVRS - Inspection 0999*/ CAN NOT USE SADDLE TAPS ON PRIVATE SEWER SYSTEM. MUST PROVIDE DIRECTIONAL FITTINGS. |