Inspection History Details
Inspection Status: Approved
Inspection History: INSP - FOLLOW UP CODE ENFORCE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/08/2005 | INSP - FOLLOW UP CODE ENFORCE | Approved | VISITED SITE MET WITH OWNER, TOOK PICTURES. WALKED INTERIOR AND EXTERIOR OF STRUCTURE. BASEBOARDS RECTERS WERE INSTALLED PER CODE REQUIREMENTS AND INSPECTED BY DSD. WORK UNDER PERMITS T04EL02502. ALL VIOLATIONS HAVE BEEN ABATED. OWNER HAS ABATED ALL, CLOSE CASE MARK COMPLIANCE. | |
| 01/21/2005 | INSP - FOLLOW UP CODE ENFORCE | Approved | VISITED SITE ON FW/UP INSPECTION, MADE CONTACT WITH OWNER, WALKED INTERIOR, PROGRESS HAS BEEN MADE. VIOLATION ABATED FROM N.P.O. ISSUED 11/18/04 ARE AS FOLLOWS. 1) TC. SEC. 16-11 BUILDING INTERIOR C ELECT. SYS. 1&2: NEW ELECTRICAL SERVICE HAS BEEN INSTALLED THOUGHOUT STRUCTURE, NEW RECEPTACLES, NEW EXTERIOR SUB PANELS. (2) TC. SEC. 16-11 (B) HEATING SYSTEMS: NOT ABATED. (3) TC. SEC. 16-11 BUILDING INTERIOR SURFACES & FEATURES 1,2,3,&4: A - ABATED - REFINISHED. B - ABATED - NEW EXHAUST FAN INSTALLED. C - NOT ABATED. D - ABATED - CEILING PATCHED & IS BEING REFINISHED. E - ABATED - WALL REPAIRED & REFINISHED. F - NOT ABATED G - ABATED - INTERIOR SURFACES HAVE BEEN REPAINTED. (4) TC. SEC. 16-12 BUILDING & STRUCTURES EXTERIOR (A) EXTERIOR SURFACES: 1) WEATHER PROTECTION A - ABATED - NEW WINDOW PANES INSTALLED. B - NOT ABATED (5) TC. SEC. 16-11 PLUMBING SYS. 3&4 A - ABATED - NEW SHOWER FIXTURES. B - ABATED - LINES CLEARED. C - ABATED - VIOLATION REMOVED, TC. PERMITS REQUIRED FOR HOT WATER HEATER ABATED. (6) TC. SEC. 16-12 (C) BUILDING & STRUCTURES: TC. SEC. 16-4 PERMITS REQUIRED: ABATED - ACCESSMENT FROM ARCHITECT APPROVED 2ND ROOF STRUCTURE. ILLEGALLY ATTACHED PORCH HAS BEEN REMOVED. (2) TC. SEC. 16-12 (C) BUILDING & STRUCTURES CONSTITUTING A NUISANCE BURNT GARAGE STRUCTURE HAS BEEN REMOVED. VIOLATION HAS BEEN ABATED. OWNER HAS MADE GOOD PROGRESS ON ABATING VIOLATIONS. WILL GRANT 30 DAY EXTENTIONS FOR REMAINING VIOLATIONS. |
|
| 11/17/2004 | INSP - FOLLOW UP CODE ENFORCE | Violation | MET W/OWNER & STRUCTURAL ENGINEER WALKED SITE & INTERIOR OF STRUCTURE. ENGINEER REQUESTED AN AREA OF CEILING BE REMOVED TO SURVEY EXISTING ROOF. OWNER HAD SECTION OF DRYWALL REMOVED IN LIVING ROOM AREA. APPEARS EXISTING ROOFING CONSIST OF 2 LAYERS OF 1/2'' GYPSON BOARD WAS USED WITH POSSIBLE GO ROOF ROOFING PAPER. STRUCTURAL ENGINEER REQUESTED REMOVAL OF CEIL SECTION FOR VERIFICATION OF BARRING BEAM THROUGH CENTER OF STRUCTURE. APPEARS BEAM MAY HAVE BEEN PICED TOGETHER. FINAL DETERMINATION WILL BE ADDRESSED BY ENGINEER. ROOF STRUCTURE WAS ALSO CHECKED. ROOF IS PITCHED, ENGINEER WILL REQUIRE ACCESS TO SPACE IN BETWEEN EXISTING ROOF ASSEMBLY & ADDED ROOF ASSEMBLY. ON SITE ASSESSMENT WAS MADE THAT WALLS (EXTERIOR) WERE WOOD FRAME CONSTRUCTION. ENGINEER WILL PROVIDE COMPLETED WRITTEN ASSESSMENT TO D.N.R. & OWNER. PICTURE WERE TAKEN. OWNER HAS REMOVED HAZARDOUS BURNT STRUCTURE & ABANDONED VEHICLE. N.O.V. WAS HAND DELIVERED & SIGNED BY OWNER. UNIT IS STILL VACANT & SECURED. WILL DO FW/UP IN 30 DAYS. |