Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T04CM05032
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/01/2006 | ENGINEERING - FINAL | Approved | ||
09/21/2006 | ENGINEERING - FINAL | Partial Approval | I MET WITH KIM ACORN, TL ROOF, THE OWNER AND TERRY MOORE THE LANDSCAPE DESIGNER. 1. COMPLETE ROCK RIP RAP STABILIZATION AND REPAIR EROSION DAMAGE. 2. PROVIDE BARRICADE RAILING AT SIDEWALK SCUPPER. |
|
10/18/2005 | ENGINEERING - FINAL | Partial Approval | TEMPORARY C OF O APPROVED. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTIONS #09190 FOR TO4BU03031 AND T04BU02006 ARE COMPLETED AND APPROVED. 1. BUILD TOP OF WALL TO ELEVATION 2618/FLUSH WITH CURB (SEE DETAIL 3 PAGE C2.1) 2. PROVIDE IMPERVIOUS SOIL CAP ON 6:1 LANDINGS (SEE DETAIL 3 PAGE C2.1) 3. PROVIDE CONCRETE COLLAR, CONTROL JOINTS AND CUT THE 24" PIPE FLUSH WITH THE WALL (SEE DETAIL 5 PAGE C2.1) 4. PROVIDE THE FIRST ANNUAL R/D BASIN CERTIFICATION LETTER FROM AZ REGISTERED P.E. PER NOTE ON PAGE C3.1 5. CORRECT PONDING WATER ON ASPHALT SURFACES (SEE FIELD PLAN). 6. PROVIDE CROSSWALK STRIPPING AT THE SOUTHEAST CORNER OF THE FELLOWSHIP HALL. 3. CLEAN-UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. 7. PROVIDE ROCK STABILIZATION: 2:1 SLOPES = ROCK RIP RAP ON FILTER FABRIC 1:1 SLOPES = GROUTED ROCK RIP RAP COMPLETE ALL SITE WORK AS SHOWN ON THE SITE AND GRADING PLANS. |
|
09/23/2005 | ENGINEERING - FINAL | Partial Approval | BARRICADING INCOMPLETE OUTSIDE WORK OK FOR TEMP C OF O |
|
09/22/2005 | ENGINEERING - FINAL | Denied | NOT READY FOR INSPECTION. COMPLETE ALL SITE WORK AS SHOWN ON THE SITE AND GRADING PLANS |