Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/10/2005 |
PLUMBING - FINAL |
|
Approved |
IVRS - Inspection :* CORRECTIONS HAVE BEEN MADE AS PER LAST REQUEST. ALL TESTING ON BACKFLOW DEVICES COMPLETE. FINAL OK STOI |
| 02/09/2005 |
PLUMBING - FINAL |
|
Not ready for Inspection |
IVRS - Inspection :*1) ALL DRAINAGE TO BE GRAVITY TO CORRECT RECEPTOR. 2) ICE MACHINE BIN & UNIT TO BE INDEPENDENT DRAINS. 3) ALL BACKFLOWS TO BE INSTALLED & CERTIFICATIONS ON SITE FOR INSPECTOR. 4) SINK PO51 REQUIRE EXPOSEING OF CLEANOUT |