Permit: T04CM04772

Parcel: 11005314C

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T04CM04772

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
03/14/2006 ENGINEERING - FINAL Approved PHASED DEVELOPMENT PLAN APPROVED BY CRAIG GROSS
11/10/2005 ENGINEERING - FINAL Partial Approval TEMPORARY C OF O APPROVED. SEE COMMENT # 2-6 LISTED FOR PREVIOUS INSPECTION
11/09/2005 ENGINEERING - FINAL Denied 1. COMPLETE CURB INSTALLATION AT PARKING AREAS.
2. BARRICADE ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING TO PREVENT PEDESTRIAN/PUBLIC ACCESS.
3. COMPLETE ROCK RIP RAP IN DRAINAGE AREAS.
4. CONSTRUCT DRAINAGE SWALE AND (5) CURB OPENINGS AT THE SOUTH PERIMETER.
5. DEPRESS LANDSCAPE AREAS MAX. 6" FOR STORMWATER HARVESTING. (SEE GRADING PLAN NOTE #13)
6. PROVIDE A LETTER OF CERTIFICATION FROM ARIZONA REGISTERED P.E. STATING THAT THE DRAINAGE WAY HAS BEEN CONSTRUCTED IN ACCORDANCE WITH THE APPROVED PLANS. SEE GRADING PLAN NOTE#12.C. AND CHAPTER XIV SEC. 14.2(7).
7. PROVIDE A COPY OF THE REVISED GRADING PLAN FOR THE NEXT INSPECTION.
8. CALL FOR FINAL GRADING INSPECTION #09190 FOR T04BU00623
9. PROVIDE A COPY OF THE TEMPORARY C OF O BONDING LETTER DATED 11-4-05.
10/19/2005 ENGINEERING - FINAL Denied NOT READY FOR INSPECTION
1. COMPLETE SITE WORK INCLUDING ALL PERIMETER LANDSCAPING AND SIDEWALKS FOR THIS PROJECT. (SEE GRADING PLAN).
2. BARRICADE ALL AREAS WHERE ON-GOING OR UN-FINISHED CONSTRUCTION IS OCCURRING.
3. PROVIDE A PHASED CONSTRUCTION PLAN FOR THIS DEVELOPMENT THAT HAS BEEN APPROVED BY THE C.O.T. ZONING AND ENGINEERING DIVISIONS.