Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/16/2006 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 01/18/2006 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1. 2" YARD WATER LINE FROM METER LOCATION TO BLDG. SERVICE IS OK 2. NOTE SHALL SEE APPROVED DRAWING ON SITE WATER LINE COVER @ YOUR OWN RISK |
|
| 07/14/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* (3) 4" BUILDING DRAIN STUBS IN 5' & OUT 5' OF BUILDING ON NORTH SIDE WATER TEST OK. 1) WILL NEED TO VIEW 2 WAY CLEANOUT INSTALL & CONTINUATION OF BUILDING SEWER. (7 ) 3'' RAIN DRAIN & OVERFLOW RAIN DRAIN STUBS UP 2' AND OUT OF COLUMNS ON SOUTH SIDE WATER TEST OK.1) WILL NEED TO VIEW CONTINUATION OF RAIN DRAIN PIPING WITH TEST. 2" H20 STUB UP & OUT OF BUILDING 5' SOUTH EAST CORNER 20 + PSI TEST OK | |
| 07/13/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* PROVIDE CITY APPROVED PLUMBING PLAN FOR YOUR JOB. |