Permit: T04CM04561


Addresses:

370 N PANTANO RD


Inspection Status: Approved

Inspection History: PLUMBING - FINAL

Permit Number - T04CM04561

Inspection Description - PLUMBING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
09/01/2006 PLUMBING - FINAL Approved IVRS - Inspection :*
08/31/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
9:30 AM
- STILL WORKING ON WH CORRECTIONS
- SEVERAL CLEAN OUTS NOT COMPLETE
- HB MISSING HANDLE AND NOT SECURE
- FP MISSING LOG VALVE TRIM
08/30/2006 PLUMBING - FINAL Denied IVRS - Inspection :
See detailed listing on site.| 999*
SOUTH HALF OF PROJECT INSPECTED
UNITS 100-118 AND 200-220 OK EXCEPT
#106 - CRACKED FITTING ON T&P
#120 - T&P BLOCKED, INSTALL PROPER CO PLUGS
#119 - DRIP ON T&P INSTALL PROPER CO PLUGS

WH AT LAUNDRY
- FLEX IS UNDERSIZED, GAS PIPING NEEDS SUPPORT.
- EXP. TANK NOT ADEQUATELY SUPPORTED
- ON WATER PIPING USE CORRECT SIZE & TYPE OF SUPPORTS
- PVC PIPING NOT CORRECTLY INSTALLED. PVC IS TO BE PRIMED BEFORE SOLVENT CEMENTING.
- EXPOSE CLEANOUTS AT MS & LAUNDRY
- PROTECT ALL EXTERIOR PLASTIC FITTINGS W/LATEX PAINT
08/29/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
- HBS VAC BREAKERS AND PACKINGS ARE LEAKING
- REPAIR ON SEWER LINE IN PROGRESS
- CHINA BOWL CAPS MISSING
- UNABLE TO INSPECT LAUNDRY WH BECAUSE OF FRESH CONCRETE
- SEE NOTES FROM 8/23 AND 8/15 REGARDING WH
- CLEANOUT MISSING IN MULTI-PURPOSE RM. ALSO PERM CAP PIPING NOT USED.
08/25/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
COMPLETE ALL PLUMBING FIXTURES HAVE A CONTACT PERSON ON SITE OR LEAVE A MESSAGE PHONE #
08/23/2006 PLUMBING - FINAL Not ready for Inspection IVRS - Inspection :*
- NOT A COMPLETE PUNCH LIST
- PLUMBING FIXTURES INSTALLED IN MOST AREAS. MANAGERS ROOM AND KITCHEN AREA NOT READY.
- CORRECT ICE MAKER BOX IN KIT. AREA
- SUPPORT EXP. TANK AND PIPING AT LAUNDRY WH
- PROVIDE SPECS FOR DIRECT VENT WH. SOLVENT WELD PVC JOINTS REQUIRE THE USE OF PVC PRIMER.
- SUPPORT CPVC T&P PIPING AT WHS THAT HAVE PIPING LOCATED IN AREAS THAT COULD BE DAMAGED.
- T&P TERMINATION AT MOP SINK REQUIRES AN AIR GAP
- TRIM OUT ALL CLEANOUTS. C/O PLUGS SHALL BE MADE WATER AND GAS TIGHT BY THE USE OF APPROVED THREAD SEALANTS.
- TUBULAR BRASS TRAPS NOT ALLOWED ON URINALS.