Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
Permit Number - T04CM04561
Inspection Description - PLUMBING - SEWER HCS CONNECT
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/28/2006 | PLUMBING - SEWER HCS CONNECT | Approved | IVRS - Inspection :* | |
08/25/2006 | PLUMBING - SEWER HCS CONNECT | Not ready for Inspection | IVRS - Inspection :* PROVIDE AUTHORIZATION TO DISCHARGE FROM P.C.D.E.Q |
|
08/23/2006 | PLUMBING - SEWER HCS CONNECT | Not ready for Inspection | IVRS - Inspection :* | |
04/14/2006 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* MANHOLE #2 VACUUM TEST OK |
|
11/23/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 1) MAN HOLE BASES HABE BEEN POURED 2) OK TO STACK |
|
11/22/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8" SITE SEWER FROM EAST BLDG TO NORTH BLDG IS OK UP TO M H # 4 OK TO BACKFILL TRENCH. |
|
11/18/2005 | PLUMBING - SEWER HCS CONNECT | Not ready for Inspection | IVRS - Inspection :*NO CHANGE FROM 11/17/05 | |
11/17/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8 SDR 35 GOING NORTH FROM MANHOLE # 3 WITH 4" SDR STUB UP FOR HCS CONNECTION APP 130" NORTH CONTINOUS 26' NORTH FROM THIS, TO BE CONTINUED | |
11/16/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8" SDR 35 FROM MANHOLE # 3 APP. 60' NORTH TOWARD MANHOLE # 4 OK | |
11/15/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8" SITE SEWER FROM M.H # 2 TO M.H # 3 IS OK | |
11/12/2005 | PLUMBING - SEWER HCS CONNECT | Not ready for Inspection | IVRS - Inspection :* | |
11/09/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8'' SITE SEWER FROM M.H # 2 UPSTREAM 40' IS OK 6" SITE SEWER FROM M.H # 2 UPSTREAM TO BLDG. SERVICE HCS IS OK |
|
11/08/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8" SITE SEWER FROM M.H #2 UPSTREAM TO PRIVATE M.H # 2 IS OK OK TO BACKFILL THE TRENCH 40' OF DUCTILE IRONG PIPE IS OK IN BASIN AREA SHALL VERIFY AIR PRESSURE TEST @ A LATER TIME |
|
11/07/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 1) HAD A PRE-CON MEETING WITH UTILITY CONTRACTOR ON SITE SEWER |
|
11/04/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :*8" SDR 35 STUBBED OUT OF NEW MANHOLE #1 APP.3' OK |