Inspection History Details
Permit: T04CM04561
Inspection Status: Approved
Inspection History: ELECTRIC - ABOVE CEILING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/18/2006 | ELECTRIC - ABOVE CEILING | Approved | IVRS - Inspection :* | |
| 09/08/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 09/06/2006 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 09/05/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK PVC CONDUIT POLE IN POLE IN FRONT OK CORRIDOR AND REC CENTER SOUTH ABOVE CEIL OK TMPP MANAGERS UNIT |
|
| 09/01/2006 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* OK PVC POLE TO POLE EAST/FRONT - FINISH AT REC CENTER & IN FRONT OF MANUAL QUARTERS. 1. FIXTURES TO BE ATTACHED TO GRID 410.16 IF MFG CLIPS USED THEY MUST BE EFFECTIVE. |
|
| 08/31/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK TO TILE LOBBY & CORRIDOR NORTH OK PVC POLES SOUTH |
|
| 08/29/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 08/28/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK TO REENERGIZE "MPA, MPB, MPC" OK SOUTH & EAST BUILDING ABOVE CEILING HALLWAYS |
|
| 08/25/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* | |
| 08/22/2006 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* | |
| 07/05/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK CANS SOFFIT MAIN ROOM REC CENTER SUPPORT VDV CABELING |
|
| 06/26/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1) OK 2 CORRIDOR TO COMM BLDG |
|
| 06/23/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK CANS ON PORCHES COMMUNITY BUILDING. 1. SUPPORT VDV CABELING CORRIDORS AND IN BLDG. |
|
| 04/03/2006 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | IVRS - Inspection :* MEET WITH CONTRACTOR TO ANSWER QUESTIONS. |
|
| 03/22/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* 1. SECURE SE CABLE PVC CONDUITS 2. BUILDING INSPECTOR TO CHECK FIRE PENETRATIONS 3. PROVIDE MANUFACTURERS GROUND CLIP FOR BOXES 4. INSTALL VDV CABLING TO INSPECT OK 1ST LID 1ST & 2ND FLOORS NORTH BUILDING. |
|
| 03/16/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :* OK 2-2" PVC FROM 400A EAST BLDG TO "HPB" OK NM CABLE & BOXES SOUTH & EAST BUILDING CEILINGS 1. BUILDING INSPECTOR TO CHECK FIRE PENETRATIONS 2. PROVIDE GROUND FOR BOX FROM MANUFACTURER 3. INSTALL VDV CABELING TO INSPECT 725.6 & 800.6 & 760.6 4. SECONDARY RUN TO TRANSFORMERS TO BE IN A LISTED RACEWAY AND EXPOSED FOR INSPECTION |
|
| 02/22/2006 | ELECTRIC - ABOVE CEILING | Partial Approval | IVRS - Inspection :*SOUTH & EAST BUILDING 1ST FLOOR HAL CORRIDOR OK FOR 1ST LAYER OR DRYWAL |