Permit: T04CM04552

Parcel: 140384000


Addresses:

5857 E CHAUCERS DR

Inspection Status: Approved

Inspection History: EXT METAL CLIPS/EXT SHEATHING

Date Description Inspector Results Comments
02/09/2005 EXT METAL CLIPS/EXT SHEATHING Approved IVRS - Inspection :*
1) NOTE: AT REAR PORCH/BEDROOM NEED SHEAR TRANSFER DETAIL, VAULTED ROOF TO FLAT CEILING EACH SIDE OF SHEARWALL
01/24/2005 EXT METAL CLIPS/EXT SHEATHING Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) INCOMPLETE-ITEMS NOT COMPLETE
01/20/2005 EXT METAL CLIPS/EXT SHEATHING Not ready for Inspection IVRS - Inspection :*
1) NOT READY, CANCELLED PER CONTRACTOR
01/18/2005 EXT METAL CLIPS/EXT SHEATHING Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) SEE LAST INSPECTION
2) SHEAR PANELS IN GARAGE NOT PER DETAIL
3) NO TRUSS CALCS
4) NO ACCESS TO ROOF
01/10/2005 EXT METAL CLIPS/EXT SHEATHING Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) ITEMS NOT CORRECTED
2) STOPPED INSPECTION
01/07/2005 EXT METAL CLIPS/EXT SHEATHING Denied IVRS - Inspection :
See detailed listing on site.| 999*
1) SW7 REQUIRES 3"-12" NAILING WITH 5/8" ANCHOR BOLTS AT 24" CENTERS
2) STRAP PLUMBING EXTERIOR BOTTOM PLATES
3) STUDS EXCESSIVELY SPLIT-DAMAGED ARSP4'S
4) PATIO BEAM TO POSTS REQUIRE EPC'S ON 2 (2 X 6) STUDS
5) OPTIONAL TRUSSED PATIO REQUIORES 4 X 10 BEAM WITH EPC'S AT BEARING
6) 8D'S AT 6" ON CENTER SPACING REQUIRED THROUGH ROOF SHEATHING INOT 2 X BLOCKS AT TRUSS BEARING
7) INSTALL A.35'S BOTTOM CHORD TRUSSES AND 16D TOE NAILS TO BEARING AT SW3 AT 24" ON CENTER SPACING
8) NEED LADDER TO INSPECT ROOF
9) SHEARWALL TRANSFER INCOMPLETE
10) STOPPED INSPECTION