Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T04CM04534

Parcel: 13819045A

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
09/21/2006 ENGINEERING - FINAL Approved Contractor addressed all items.
10/18/2005 ENGINEERING - FINAL Partial Approval OK for temp C of O. Temp expires in 90 days.
Contractor needs to finish basin area. If basin area not finished in 90 days a 3rd. Temp C of O will not be issued.
Also contractor will need to provide a barrier of some type for all areas around basin that have more then 2 feet of depth and steeper then 4 to 1 slpoes.
Keep all construction activity separated from public access.
07/19/2005 ENGINEERING - FINAL Denied TEMP C OF O PER LARRY LOPEZ
07/06/2005 ENGINEERING - FINAL Denied Site not ready.