Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/07/2005 | PLUMBING - SEWER HCS CONNECT | Approved | IVRS - Inspection :* 1) VERIFICATION OF GRADE AND PDEQ CERTIFICATION TURNED IN |
|
| 04/13/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 1) 4" BLDG SEWER FOR NORTH SIDE OF BLDG. ONLY IS OK. 2) SOIL WATER TEST IS OK. 3) OK TO BACKFILL TRENCH. | |
| 04/08/2005 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 1) AIR PRESSURE TEST IS OK 2) 8" SITE SEWER FROM P.L UPSTREAM TO MANHOLE #1 IS OK AS NOTED ON PLAN 3) OK TO BACKFILL TRENCH. 4) SHALL REQUIRE SEWER LINE TO BE SHOT FOR VERIFICATION OF GRADE EVERY 50' |