Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T04CM03776
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2005 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 06/02/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/14/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* WFI FOOTING FOR STAIR WAL NORTH OF RAMP OK | |
| 04/13/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/12/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* COPIES OF SOIL REPORTS AND CONCRETE CYLINDER BREAKS RECEIVED FROM "??" OF P.W WITHERS. I WILL REVIEW THIS WEEK. | |
| 04/11/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) MEETIN HELD WITH JASON MANCHESTER OF SPEEDIE AND ASSOCIATES ON 4/7/05. PER OUR CONVERSATION, THE SUPPLIED SPECIAL INSPECTION DAILY REPORTS, AND THE RFI REVISIONS SUPPLIED BY PAUL KULKA OF PAU KOEHLER STRUCTURAL CONSULTING ENGINEERS INC . I AM SATISFIED THAT THE CAISSONS, CAISSONS CAPS, GRADE BEAMS AND MASONRY WAL FOOTING WERE INSTALLED PER PLAN | |
| 04/06/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :**I NEED MORE INFORMATION /INSPECTION REPORTS FOR THE FOLLOWING 1) GRADE BEAM POURS FRO SW3,SW4, AND SW6. I NEED DAILY INSPECTIONS REPORTS FOR ALL 3 POURS. 2) CAISSON C/301 I HAVE NO REPORT OF CONCRETE PLACEMENT. ( 6 KSI REQUIRED PER RFI). 3) GRADE BEAM POUR LINE A/10.2-11. 4) CONCRETE PLACEMENT REPORTS FOR MODIFIED GRADE BEAMS AT C/2 AND C/3 ( NOTES DATED 1-10-05 INDICATE 6KSI CONCRETE POURED AT C/2-RFI CALLS FOR 8 KSI) IF YOU COULD PLEASE PROVIDE DAILY REPORTS FOR EACH OF THE ABOVE POURS AND COPIES OF YOUR CONCRETE CYLINDER BREAKS THEN I CAN WRAP UP OUR FOOTING INSPECTION/ REVIEW | |
| 04/04/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) REVIEWED SPECIAL INSPECTION REPORTS DATED 12/09/04 THROUGH 3/25/05. THERE ARE SOME AREAS WHERE THE REPORTS SEEM TO BE MISSING. MEETING WILL BE SCHEDULED WITH SPECIAL INSPECTOR JUSTIN MANALESTER TO GO OVER DISCREPANCIES. 2) ALL CAISOON FOOTINGS APPEAR TO HAVE BEEN COMPLETED PER STRUCTURAL DRAWINGS OR ENGINEER MODIFIED DRAWINGS FOR FIELS CONDITIONS. 3) I NEED MORE INFORMATION AT THIS TIME FOR SHEAR WALL GRADE BEAMS, SOME WALL FOOTINGS AND A GB1 ON LINE A/10.2-11 | |
| 04/01/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 1) REVIEWED PLANS AND SPECIAL INSPECTION REPORTS DATED NOV 20 THROUGH DECEMBER 3, 2004. 2) FOLLOWING CAISSONS OK. LINE B-2, 3, 5, 8, 10, 12 LINE A- 9.3, 8, 7.3, 6.7, 10.3, 1, 1.5, 2, 2.3, 2.6, 3.0, 5, 4, 10, 10.7 LINE B.7- 2, 3, 4, 6, 7, 9, 10, 11, 12 LINE C- 1.9, 2.1, 4, 6, 7, 9, 10, 11 AND B.2/7, B.2/4,B.3/4,B.7/7,A.9/4,,A.9/9,A.9/7,A.8/6,B.2/9 3) I NEED TO SEE RFI FOR MISSING SPECIAL DOWELS B.3/9, A.8/9,A.8/4,A.8/7 |
|
| 03/31/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* REVIEWED SPEC. INSP REPORTS 11-16 THRU 11-19-05. CAISSONS A/8.3, A/9.7, A/7.7, A/6.3, A/7, A.8/9, B10, B11, B12, C/9 A/11, A/10.3, A/9, A/8.3 CONFIRMED OK PER SI REVIEW. | |
| 03/30/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* PICKED UP SET OF APPROVED PLANS FROM MARK ( D.L WITHERS) PICKED UP COPIES OF SPECIAL INSP. REPORTS. MADE GENERAL FIELD INSPECTION OF SITE CONDITIONS. | |
| 03/29/2005 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* |