Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T04CM03776


Addresses:

110 E PENNINGTON ST


Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Permit Number - T04CM03776

Inspection Description - EXCAVATION/LAYOUT REBAR & ZON

Inspection Status - Approved

Date Description Inspector Results Comments
06/09/2005 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
06/02/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/14/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* WFI FOOTING FOR STAIR WAL NORTH OF RAMP OK
04/13/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
04/12/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* COPIES OF SOIL REPORTS AND CONCRETE CYLINDER BREAKS RECEIVED FROM "??" OF P.W WITHERS. I WILL REVIEW THIS WEEK.
04/11/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* 1) MEETIN HELD WITH JASON MANCHESTER OF SPEEDIE AND ASSOCIATES ON 4/7/05. PER OUR CONVERSATION, THE SUPPLIED SPECIAL INSPECTION DAILY REPORTS, AND THE RFI REVISIONS SUPPLIED BY PAUL KULKA OF PAU KOEHLER STRUCTURAL CONSULTING ENGINEERS INC . I AM SATISFIED THAT THE CAISSONS, CAISSONS CAPS, GRADE BEAMS AND MASONRY WAL FOOTING WERE INSTALLED PER PLAN
04/06/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :**I NEED MORE INFORMATION /INSPECTION REPORTS FOR THE FOLLOWING 1) GRADE BEAM POURS FRO SW3,SW4, AND SW6. I NEED DAILY INSPECTIONS REPORTS FOR ALL 3 POURS. 2) CAISSON C/301 I HAVE NO REPORT OF CONCRETE PLACEMENT. ( 6 KSI REQUIRED PER RFI). 3) GRADE BEAM POUR LINE A/10.2-11. 4) CONCRETE PLACEMENT REPORTS FOR MODIFIED GRADE BEAMS AT C/2 AND C/3 ( NOTES DATED 1-10-05 INDICATE 6KSI CONCRETE POURED AT C/2-RFI CALLS FOR 8 KSI) IF YOU COULD PLEASE PROVIDE DAILY REPORTS FOR EACH OF THE ABOVE POURS AND COPIES OF YOUR CONCRETE CYLINDER BREAKS THEN I CAN WRAP UP OUR FOOTING INSPECTION/ REVIEW
04/04/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* 1) REVIEWED SPECIAL INSPECTION REPORTS DATED 12/09/04 THROUGH 3/25/05. THERE ARE SOME AREAS WHERE THE REPORTS SEEM TO BE MISSING. MEETING WILL BE SCHEDULED WITH SPECIAL INSPECTOR JUSTIN MANALESTER TO GO OVER DISCREPANCIES. 2) ALL CAISOON FOOTINGS APPEAR TO HAVE BEEN COMPLETED PER STRUCTURAL DRAWINGS OR ENGINEER MODIFIED DRAWINGS FOR FIELS CONDITIONS. 3) I NEED MORE INFORMATION AT THIS TIME FOR SHEAR WALL GRADE BEAMS, SOME WALL FOOTINGS AND A GB1 ON LINE A/10.2-11
04/01/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* 1) REVIEWED PLANS AND SPECIAL INSPECTION REPORTS DATED NOV 20 THROUGH DECEMBER 3, 2004. 2) FOLLOWING CAISSONS OK.
LINE B-2, 3, 5, 8, 10, 12
LINE A- 9.3, 8, 7.3, 6.7, 10.3, 1, 1.5, 2, 2.3, 2.6, 3.0, 5, 4, 10, 10.7
LINE B.7- 2, 3, 4, 6, 7, 9, 10, 11, 12
LINE C- 1.9, 2.1, 4, 6, 7, 9, 10, 11
AND B.2/7, B.2/4,B.3/4,B.7/7,A.9/4,,A.9/9,A.9/7,A.8/6,B.2/9
3) I NEED TO SEE RFI FOR MISSING SPECIAL DOWELS B.3/9, A.8/9,A.8/4,A.8/7
03/31/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* REVIEWED SPEC. INSP REPORTS 11-16 THRU 11-19-05. CAISSONS A/8.3, A/9.7, A/7.7, A/6.3, A/7, A.8/9, B10, B11, B12, C/9 A/11, A/10.3, A/9, A/8.3 CONFIRMED OK PER SI REVIEW.
03/30/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* PICKED UP SET OF APPROVED PLANS FROM MARK ( D.L WITHERS) PICKED UP COPIES OF SPECIAL INSP. REPORTS. MADE GENERAL FIELD INSPECTION OF SITE CONDITIONS.
03/29/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*