Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
07/14/2006 ENGINEERING - FINAL Approved ALL PREVIOUSLY NOTED ITEMS HAVE BEEN CLEARED AT THIS TIME. SOME SIDEWALK AND ASPHALT HAS BEEN DAMAGED DUE TO NEW PERMIT WORK STARTING ON THIS SITE ALONG THE EAST SIDE OF THE GYMNASIUM. ALL CURRENT DAMAGE WILL BE RE-INSPECTED PRIOR TO THE FINAL RELEASE OF THE C OF O'S IN THIS AREA.
03/31/2006 ENGINEERING - FINAL Partial Approval SEE PREVIOUS COMMENTS FROM 2/7/06. COMPLETE ALL ITEMS AS SHOWN ON THE APPROVED PLANS FOR THIS SITE PRIOR TO SCHEDULING A RE-INSPECTION. THIS WILL INCLUDE ALSO THE COMPLETION OF ALL GRADING AND DRAINAGE ITEMS THAT HAVE BEEN SHOWN ON THE APPROVED PLANS.
02/07/2006 ENGINEERING - FINAL Partial Approval MET WITH THE DEVELOPER ON-SITE, HE WILL BE SCHEDULING ANOTHER INSPECTION IN THE FUTURE FOR ALL OF THE REMAINING WORK ON THIS SITE. HAVE ADVISED THE DEVELOPER THAT HE NEEDED TO COMPLETE ALL AREAS PER THE APPROVED GRADING PLAN PRIOR TO ALL FINAL RELEASES FOR THIS SITE.