Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
12/07/2005 ENGINEERING - FINAL Approved ALL ISSUES FROM 11/14 INSPECTION ADDRESSED.
11/14/2005 ENGINEERING - FINAL Denied MET WITH DON WILLIAMS 471-8421 (LLOYD CONST)
-GENERAL CLEAN UP OF CONSTRUCTION DEBRIS/ROADWAY TRACKING
-ROCK RIP RAP NEEDS TO BE INSTALLED AROUND STORM DRAINS (PER PLAN) -PROTECT STORM DRAINS WITH SEDIMENT CONTROLS UNTIL RIP RAP IS IN PLACE
-ALL SPLASH BLOCKS NEED TO BE IN PLACE
-ALL CONCRETE NEEDS TO BE POURED ON EAST SIDE OF BUILDING
-CONCRETE NEEDS TO BE IN PLACE IN LOADING DOCK AREA (WEST SIDE OF BUILDING) AROUND ROOF SUPPORTS
-DIRT LOT TO THE SOUTH OF THE BUILDING NEEDS TO BE STABILIZED
-CURBING ON SOUTH WEST SIDE OF BUILDING NEEDS TO BE POURED (REPLACED IN CURB CUT AREA)