Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/02/2005 | PLUMBING - INTERMEDIATE | Approved | IVRS - Inspection :* | |
| 04/22/2005 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :* SPOKE WITH PLUMBER ON SITE CORRECTONS WILL BE MADE | |
| 04/18/2005 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999*PLUMBER TO BE ON SITE AT TIME OF REINSPECTION. |
|
| 04/12/2005 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999*INSTALL YOUR H20 PIPING PER YOUR APPROVED PLAN. |
|
| 03/30/2005 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection :* 1) REDUCED PRESSURE BACKFLOW DEVICE HIGHER THAN 5' FROM FLOOR LEVEL REQUIRES PERM. LADDER & PLATFORM FOR SERVICE. 2) RPB DEVICE CAN ONLY SUPPLY (1) DOWN STREAM FIXTURE NOT MULTIPLE FIXTURES AND IS REQUIRED ON CARBONATER FOR SODA. 3) DOUBLE CHECK VALVES ARE REQUIRED ON DIRECT CONNECTION FOR H20 TO COFFE MAKERS, SOME ICE MACHINES, AND H20 SUPPLY TO NON-CARBONATED BEVERAGES THAT HAVE DIRECT CONNECT H20 TO THEM |