Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T04CM02682
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/03/2008 | ENGINEERING - FINAL | Approved | LETTER IN FILES | |
08/09/2006 | ENGINEERING - FINAL | Partial Approval | OK for Temp C of O. Contractor need to supply letter from engineer certifing drainage way. |
|
05/05/2006 | ENGINEERING - FINAL | Denied | Contractor needs to address: 1- Complete punch list from 3/31/06. 2- Complete all HC ramps. 3- install trucated domes on HC ramps. 4- Separate construction activity from public access. 5- Build trash enclosure per COT standard 6.01. 6- Provide letter from engineer in regards to drainage. 7- Bolt down all scupper lids. 8- Complete all sidewalks per approved plans. |
|
03/31/2006 | ENGINEERING - FINAL | Denied | This is not a final punch list. Contractor needs to address: 1- Clean 15th. Street. 2- Clean Russell Ave. 3- Separate construction activity from public access. 4- Provide postive drainage away from building. 5- Clean all construction wash out from site. 6- Clean parking area. 7- Complete all site work. 8- Install trucated domes on all H.C. ramps 9- Install all H.C. ramps per C of T standards. 10- Install bike parking. 11- Replace all broken concrete on all H.C. ramps. 12- Install bollards and gates in trash enclosure. 13- Install weep holes in block wall to grade for proper drainage. Remove screens. 14- Complete all striping. |