Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2005 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* 1) OK TO BACKFILL TRENCH |
|
| 07/21/2005 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* 1) SOIL WATER TEST IS OK 2) NOTE: BLDG DRAIN IS STUBBED OUT OF BLDG 2' ONLY 3) OK TO BACKFILL TRENCH 4) NOTE: CANNOT BUNDLE HOT AND COLD WATER LOOP. SHALL SEPERATE THESE LINES AND CANNOT BE TOUCHING ALONG SIDE OF EACH OTHER 5) CALL FOR INSPECTION WHEN WATER LINES HAVE BEEN SEPERATED |
|
| 07/20/2005 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NO APPROVED PLANS ON SITE 2) CANNOT BUNDLE THE HOT AND COLD WATER TOGETHER FOR U.G. WATER LOOP |