Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/02/2005 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* PIPI WRAPS OK FOR CONCRETE. RAIN DRAIN STUBS WILL REQUIRE AIR TEST AT LATER DATE COVER AT OWN RISK |
| 01/24/2005 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* ADDITION OF 4" IN LINE CLEANOUT OK 1) CALL IN 03005 FOR VIEWING OF PIPE WRAPS PRIOR TO CONCRETE POUR. |
| 01/21/2005 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* 6PSI AIR TEST UNDERGROUND ONLY PARTIAL APPROVAL 1) NEED TO HAVE 4? FULL SIZE CLEANOUT BETWEEN END OF LINE ON SOUTH END AND WYE BRANCH BECASUE OF EXCESS OF 100' FEET. |