Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/01/2005 | PLUMBING - FINAL | Approved | ||
| 02/25/2005 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* PROVIDE BACKFLOW CERTIFICATION | |
| 02/23/2005 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection :* PLEASE INSTALL SUPPLY AS PER APPROVED PLAN TO MISTER SYSTEM. PLAN CALLED FOR 3/4-1/2 HAS BEEN INSTALLED. ALSO PROVIDE PROPER BACKFLOW PROTECTION FOR WATER TO MISTING SYSTEM. AS REQUIRED BY CODE TESTING-REQUIRED ON DEVICE | |
| 11/03/2004 | PLUMBING - FINAL | Denied | IVRS - Inspection : See detailed listing on site.| 999*/CONNECT GAS PIPE TO HEATERS AS PER PLANS. DO NOT USE FLEX. SEE SECTION 1 ON PLANS. PROVIDE PLUGS IN 3 EXISTING MISTERS. |
|
| 11/02/2004 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/04/2004 | PLUMBING - FINAL | Not ready for Inspection | IVRS - Inspection :*/ 1) PLEASE SEE APPROVED PLAN. PLAN CALLS FOR 3/4 TO HEATER 1/2 HAS BEEN INSTALLED. ALSO SEE DETAIL AT METER SET. PLEASE INSTALL VALVES ETC... AND PROVIDE TEST OR PROVIDE AN APPROVED REVISED PLAN AT TIME OF NEXT INSPECTION |