Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 08/04/2004 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :*/ 1) SOIL WATER TEST IS OK 2) P.O.C. OF NEW BLDG DRAIN TO EXISITNG BLDG DRAIN IS OK 3) OK TO BACKFILL TRENCH 4) NOTE: WASTE AND VENT SYSTEM HAS BEEN TESTED UP TO ROOF |
| 07/28/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :*(1) BACKFLOW PREVENTER AND FINAL CONNECTION TO METER IS OK. (2) OK TO BACK FILL TRENCH. |