Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/20/2005 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
| 10/19/2005 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) NO AIR PRESSURE |
|
| 10/12/2005 | PLUMBING - GAS PRESSURE TEST | Partial Approval | get plans revised so that it shows gas line is not under slab | |
| 05/19/2005 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 1) FROM METER TO OUTSIDE OF ADDITION |
|
| 12/15/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 1) FROM EXISTING ? TO PROPOSED ADDITION 2) VERIFY THAT EXISTING GAS LINE IS ADEQUATE TO SUPPLY NEW ADDITION SUBMIT LAYOUT OF EXISTING GAS LINE TO DSD FOR APPROVAL |