Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 10/01/2004 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection :* 1) 4RD ??PVC SEWER FROM 2 POINTS OF CONNECTION ( SANITARY WASTE, AND GREASE WASTE) THROUGH INTERCEPTOR AND SAMPLING PORT, WITH SANITARY SEWER TIED IN DOWNSTREAM OK. VENT TO BE CONNECTED DOWN STREAM OF INTERCEPTOR. OK TO COVER SEWR- NEED TO SEE VENT. ROUGH SOIL APP. |
| 09/15/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* 1) CHICAGO LOOP CONNECTION MADE OK WATER TEST ONE RISER TO TEN FEET. 2) OK TO BACKFILL |
| 09/14/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection :* 1) ABS DWV REQUIES 2% GRADE-PROVIDE INVERT OF SEWER TO JUSTIFY 1%. 2) PLAN CALLS FOR TYPE " K" UNDERSLAB. 3) CHICAGO LOOP SHOUD HAVE NO HORIZONTAL RETURN VENT. 4) OK TO COVER SUBJECT TO WATER TEST. 5) NEED TO SEE CHICAGO LOOP REROUGHED |
| 09/13/2004 |
PLUMBING - ROUGH, SOIL |
|
Cancelled |
|
| 09/13/2004 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection :*/NOT READY FOR INSPECTION |