Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 06/11/2004 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 02/19/2004 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) PLUMBING IS NOT PER APPROVED PLAN BUT IS PER FIELD CHANGE. YOU MUST PROVIDE A COMPLETE REVISED PLUMBING PLAN BEFORE INTERMEDIATE INSPECTIONS OR PROJECT WILL BE STOPPED |
| 02/17/2004 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0999*/ 1) PLUMBING IS NOT PER APPROVED PLAN-SEE ITEM 1 FROM 2/12/04 2) NEXT FAILURE WILL BE CHARGED A REINSPECTION FEE |
| 02/13/2004 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 02/12/2004 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0999*/ 1) PLUMBING IS NOT LAYED OUT PER APPROVED PLAN. BUILD TO PLAN OR REVISE PLAN TO AS BUILT. TUB DRAIN AND VENT NOT INSTALLED. 2ND FLOOR 2" DOWN WRONG LOCATION. SECOND FLOOR 3" STACK WRONG LOCATION 2) SEWER LINE BETWEEN CLEANOUTS AND HCS HAS MORE THAN 135 DEGREE HORIZONTAL CHANGE WITHOUT CLEAN OUTS 3) SECOND FLOOR CLEANOUTS LEAKING |